Office of Planning
ADMINISTRATIVE PROCEDURES FOR
THE MANAGEMENT OF THE
SITE DEVELOPMENT PLAN PROCESS
April 2000
i April 2000
TABLE OF CONTENT
Page
1.0 OVERVIEW
2.0 GENERAL DEVELOPMENT REVIEW POLICY
3.0 PURPOSE AND INTENT
4.0 PROCESS DETAILS AND CHARACTERISTICS
4.01 Project Review Team . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
4.02 Waivers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
4.03 Required Plan Types . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
4.03.1 Sketch Plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
4.03.2 Preliminary Residential Site and Subdivision Plans . . . . . . . . . . . 5
4.03.3 Final Site and Subdivision Plans and Plats . . . . . . . . . . . . . . . . . 5
4.03.4 Minor Site Plans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
4.03.5 Administrative Review Plans . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
4.03.6 Erosion and Sediment Control Plan (Separate) . . . . . . . . . . . . . . 6
4.03.7 Comprehensive Review . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
4.03.8 Nonresidential Preconstruction Plan . . . . . . . . . . . . . . . . . . . . . . 7
4.04 Application Review Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
4.04.1 Sketch Plan Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
4.04.2 Preliminary Residential Site Plan Process . . . . . . . . . . . . . . . . . . 13
4.04.3 Preliminary Residential Subdivision Plan Process . . . . . . . . . . . . 27
4.04.03.01 Term of Validity: Preliminary Residential
Subdivision and Site Plans . . . . . . . . . . . . . . . . . . 40
4.04.4 Final Site and Subdivision Plan and Plat Process . . . . . . . . . . . . 41
4.04.5 Review and Approval Process for Simple Subdivision,
Resubdivisions, Consolidations and Family Land Transfers . . . 62
4.04.6 Review and Approval Process for Revisions to
Approved Plans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76
4.04.7 Minor Site Plan Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76
4.04.8 Administrative Plan Process . . . . . . . . . . . . . . . . . . . . . . . . . . . 77
4.04.9 Time Extensions for Application Resubmissions . . . . . . . . . . . . 78
4.04.10 Final Site Development Plan Validity . . . . . . . . . . . . . . . . . . . . 79
ii April 2000
4.05 Minimum Plan and Plat Submission Requirements . . . . . . . . . . . . . . . . . 81
4.05.1 General Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
4.05.2 Sketch Plan Minimum Submission Requirements . . . . . . . . . . . . 83
4.05.3 Preliminary Residential Site and Subdivision Plan Minimum
Submission Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84
4.05.4 Final Site and Subdivision Plan Minimum Submission
Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87
4.05.5 Subdivision and Easement Plat Minimum Submission
Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91
4.06 Regulations and Procedures Governing the Conveyance of Real
Property and Easements to Prince William County . . . . . . . . . . . . . . . . . 95
4.06.1 General Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95
4.07 Performance Bonds, Agreements and Guarantees . . . . . . . . . . . . . . . . . 96
4.07.1 Performance Agreement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 96
4.07.2 Corporate Surety Bonds . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 96
4.07.3 Extensions and Rebonding of Agreements . . . . . . . . . . . . . . . . . 98
4.07.4 Performance Bond Reductions . . . . . . . . . . . . . . . . . . . . . . . . . 100
4.07.5 Performance Bond and Agreement Final Release Procedures . . . 101
4.07.6 Maintenance Bonds . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102
4.07.7 Bond Deferral Option . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103
4.07.8 Default and Evaluation Procedures . . . . . . . . . . . . . . . . . . . . . . 104
4.07.9 Debarment of Surety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105
4.08 Land Development Permit Procedures for Final Site
Development Plans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106
4.08.1 General Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106
4.09 Violation and Shutdown Notices and Procedures . . . . . . . . . . . . . . . . . 108
4.09.1 General Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109
4.10 Priority Plan Processing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109
4.10.1 Priority Site Development Plans . . . . . . . . . . . . . . . . . . . . . . . . 109
4.10.2 Priority Building Construction Plans . . . . . . . . . . . . . . . . . . . . . 109
4.11 Expedited Plan Processing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110
4.11.1 General Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110
4.12 As-built Plans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
4.12.1 General Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 112
4.12.2 Impervious Area Measure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 112
4.12.3 Compliance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 112
4.13 Appeal of Director of Planning's Decision . . . . . . . . . . . . . . . . . . . . . . . 112
5.0 CERTIFICATE OF USE AND OCCUPANCY
1
April 2000
THE MANAGEMENT OF THE SITE DEVELOPMENT PLAN PROCESS
1.0. Overview.
This document is designed to augment the Design and Construction Standards Manual (DCSM)
and set forth the process which applicants need to follow in order to gain approval of site
development plans and pursue construction of land improvements on a parcel of land in Prince
William County. All other types of applications, such as rezonings, special use permits,
provisional use permits, building permits, etc., are discussed in other similar documents.
The organizational structure and mission are shared by both the Office of Planning and the
Department of Public Works. They are both responsible for various aspects of the site and
subdivision review, approval and land permitting process. In general, the Office of Planning,
Division of Development Services is responsible for application intake, project tracking, plan
review coordination, plan review for consistency with the Zoning Ordinance, plan review for
consistency with the nonengineering aspects of the DCSM, acting on all nontechnical DCSM
waiver requests, proffers and special use permit (SUP) conditions, plan approval, construction
bond and escrow management, and land permit issuance. The Department of Public Works,
divisions of Watershed Management and Transportation, are responsible for plan review for
consistency with the engineering/technical aspects of the DCSM, consolidations of technical
comments from all other engineering related review agencies, construction site inspection of land
improvements, field support for bond/escrow actions, and acting on all technical DCSM waiver
requests.
Various other state and County agencies are also involved in the site and subdivision plan review
process. They are the Virginia Department of Transportation (VDOT), Prince William County
(PWC) Service Authority, Health Department, OIT/Information Resources Management Division
of the Office of Information Technology (OIT), Department of Fire and Rescue, PWC School
Board, Virginia American Water Company, Dale Service Company, and the PWC Park Authority.
These agencies are requested to review plans on an as-needed basis, depending on the scope and
nature of the individual plan.
It is the stated mission of Prince William County, through the Office of Planning and the
Department of Public Works, to foster superior development through the provision of quality plan
reviews and expeditious approvals. This is accomplished, in part, through a one-stop method of
plan intake, review, approval, land permitting, and the project review team concept.
2.0 General Development Review Policy.
It is the policy of Prince William County to consider the approval of site plans and subdivision
plans and plats as part of a plan for orderly, efficient and economical growth and development of
the County.
2
April 2000
3.0 Purpose and Intent.
The requirements and procedures set forth in this document are designed and intended to make
every effort for the County to review and approve sketch plans within one review cycle,
preliminary residential plans within two plan review cycles, and final plans within a maximum of
three plan review cycles.
In considering and acting upon such site and subdivision plans and plats and in consideration of
the public health, safety, and welfare, the County may prescribe appropriate conditions and
safeguards as may be required in order that the result of its action may, to the maximum extent
possible, further express the intent of the Design and Construction Standards Manual, Zoning
Ordinance, and this document.
4.0 Process Details and Characteristics.
4.01 Project Review Team. The project review team concept, as stated above, is an integral
part of the one-stop method of site and subdivision plan review. The project review team concept
is designed to provide an applicant with clear, consistent, concise and timely plan reviews. In
addition, project review teams provide a continuity of reviewer via the utilization of a case
manager to insure that issues are resolved at their proper level and time in the process, and are not
revisited once resolved.
A. Membership and Composition. The Office of Planning's Division of Development
Services is divided into project review teams. Each project review team will be headed by a case
manager from Development Services. The case manager will serve as the project review team
chairman. The case manager will serve as the permanent project review team foundation, and will
remain continually involved with each project throughout the entire development process, until
the relevant land development permits have been issued for the project in question.
(1) The Office of Planning's Division of Development Services becomes involved with
the site development plan process (and thereby is a member of the project review team) on an
as-needed basis. If the parcel, that is the subject of a site or subdivision plan, was previously the
subject of a rezoning or SUP approval by the Board of County Supervisors (BOCS), the project
review team chairman may elect to obtain input from the Division of Development Services
relative to that approval. The need for such involvement, to assist in clarifying a proffer or SUP
condition, is determined by each team chairman. The Division of Development Services staff
member, assigned to assist the project review team chairman, will be determined by the chief of
Development Services, upon a request by the project review team chairman.
(2) The Office of Planning's Zoning Administration (ZA) Division's assistance may be
forthcoming in a manner similar to that discussed in Section 1. above for the Division of
Development Services. Specifically, this as-needed assistance to the project review team
chairman will be oriented toward official interpretations of the Zoning Ordinance, proffers, SUP
conditions, if deemed necessary by the project review team chairman.
3
April 2000
(3) The Department of Public Works' Watershed Management Division has a permanent
member on each project review team. Its staff of engineers have been assigned geographically, by
major drainage basin, by the chief of Watershed Management.
(4) The Department of Public Works' Transportation Division also has a permanent
member on each project review team. Its staff of transportation engineers have been assigned
geographically to coincide with the drainage basins utilized by the Watershed Management
Division.
(5) All the other public agencies traditionally involved in the review process will continue
to function on as-needed basis similar to that discussed in Section (1) above for the Division of
Development Services. This as-needed assistance is sought by the project review team chairman,
as has historically been done, and is directed to the particular expertise of the agency in question.
(For instance, all plat-related questions and issues are directed to the OIT/Information Resources
Management Division, along with a request to attend a specific project review team meeting.)
B. Geographic Areas. The project review teams are divided into geographic areas that
correspond to the drainage basins utilized by the Department of Public Works. Those areas are
Bull Run, Broad Run, Cedar Run/Occoquan River, Powells Creek/Quantico Creek, and Neabsco
Creek/Marumsco Creek.
C. Project Review Team Meetings. Each project review team meets at designated critical
points throughout the site development plan review process. These meetings are kept to a
minimum in order to save staff time.
D. Responsibilities of the project review team members and its chairman.
(1) The project review team meetings are held to discuss the review of the plan and to
focus on and discuss outstanding issues.
(2) The case manager/project review team chairman, in order to coordinate the overall
review and processing of an application and to ensure that agency comments do not conflict,
should be the focal point for all scheduling and should be apprised of all meetings between the
applicant and review agency representatives, whose purpose is to discuss major technical issues.
This system is designed to be coordinated by notification. To this end, the chairman may choose
not to participate in a specific discussion. However, he/she should have the opportunity to do so.
In addition, the project review team chairman is also responsible for chairing and scheduling all
project review team meetings associated with a project, and managing and coordinating the
review and approval process. The chairman will also be responsible for elevating issues, which
require discussion, to the division chiefs for resolution, following unsuccessful resolution
attempts by the project review team members, consulting with various other divisions and
departments, writing and issuing the consolidated summary review letters, and recommending a
plan for approval. The chairman also reviews the plan for conformity with the Zoning
Ordinance, compliance with proffered and SUP conditions, and the consolidation of all
nontechnical review agency comments.
4
April 2000
(3) The Department of Public Works' Transportation and Watershed Management
engineers are responsible for the engineering review of the plan. This includes a review for
conformity with DCSM technical standards, other County and state technical regulations, and
other generally accepted engineering and safe design standards. In addition, they are responsible
for consolidating all technical review agency comments and transmitting one consolidated
engineering review letter to the Division of Development Services.
(4) The Department of Public Works' site inspectors provide construction expertise to
the review process on an as-needed basis. This input is designed to help avoid plan-related
construction problems from occurring.
4.02. Waivers. When compliance with a particular site development plan requirement
contained in either the DCSM or this document unduly burdens the applicant or causes harm to an
adjacent property, the applicant may request a waiver of the requirement for consideration by the
director of Planning, the director of Public Works or the Planning Commission, depending on the
nature of the request and the stage of the application process. The applicant shall examine
alternative methods to attempt to comply with the intent of that ordinance unless otherwise
specified. Waivers of requirements of the subdivision ordinance are considered by the Planning
Commission, while waivers of site development plan requirements are considered by either the
director of Planning or Public Works. Generally, the director of Planning acts on process and
time extension waivers, while the director of Public Works acts on engineering waivers.
A. All requests for waivers are made by the applicant to the director of Planning,
accompanied by a nonrefundable fee. The request shall be in writing and state the regulation
involved, the relief requested, and the reasons the request should be granted. Four (4) sets of any
supportive plans, profiles, or drawings necessary to review the request must accompany the
submission. Generally, waiver requests must be made and acted upon prior to the submittal or
resubmittal of any subdivision or site plan, unless concurrent processing has been granted by the
reviewing authority. The County has two (2) days within which to accept or reject a waiver
application. If rejected, the application will be returned to the applicant with the reasons for the
rejection outlined in writing. Upon acceptance, the waiver application will be transmitted to the
appropriate agency(ies) for review. Action on a waiver request will be made within thirty (30)
calendar days of acceptance. Any decision on waivers by the director of Planning or the Planning
Commission is final.
B. In acting on a request where another agency has authority in the specific area of the
request, the director of Planning and the director of Public Works shall consult with such agency
(i.e., VDOT, Service Authority, etc.).
4.03. Required Plan Types.
4.03.1 Sketch Plan. These are the initial plan type submissions required for all nonresidential
projects where the total site acreage is in excess of five (5) acres (2.02 hectares). Sketch plans
may also be utilized for residential projects where no more than one hundred (100) lots or units
are proposed for the overall project. A waiver of the sketch plan requirement for residential
projects may be considered when the property is subject of a rezoning case with a substantially
proffered general development plan. Residential projects in excess of one hundred (100) lots or
5
April 2000
units will require a preliminary plan as per Section 4.03.2 of this manual. Sketch plans are used in
a single macro review process, not requiring engineering detail, designed to produce general
agreement and consensus on the design, size, access, layout, extent, and location and degree of
improvements necessary or proposed in conjunction with a proposed development. The
developer may also have the option of utilizing this process for nonresidential projects less than
five (5) acres (2.02 hectares).
4.03.2 Preliminary Residential Site and Subdivision Plans. These plan types are required for
all residential projects resulting in the creation of five (5) or more lots, unless the applicant has
chosen to submit a sketch plan, in accordance with Section 4.03.1 of this manual. If a sketch plan
has been submitted, the preliminary residential plan process may be eliminated.
Preliminary residential site and subdivision plans (preliminary plans) are meant to show the
general design of a residential site or subdivision project and its public improvements, so the
County, and when appropriate, the Planning Commission, can indicate its approval or disapproval
of the project, prior to the time the final plans and plats are designed detailing the public
improvements, utilities, etc. The County shall review the practicability of the preliminary plan and
its general design. Attention shall be given to the arrangement, location, and width of streets and
travelways, arrangement, placement, and size of structures, their general relationship to the
topography of the land, feasibility of water supply and sewage disposal, general handling of site
drainage, lot sizes and arrangement, the future development of adjoining lands as yet
undeveloped, the relationship of adjoining developed lands, and the requirements/guidelines of the
comprehensive plan, Zoning Ordinance, and subdivision ordinance. Preliminary plans are not
meant to either depict, or be reviewed for, final engineering design and details.
4.03.3 Final Site and Subdivision Plans and Plats. These plan types and any necessary
supporting documents for a proposed project constitute the complete application for construction
approval. They shall include complete and detailed engineering and layout drawings for all the
public and private improvements and utilities, in addition to any necessary ancillary calculations
required for review. Upon approval, the final plans and plats form the basis for the construction
of the project and the inspection services of the Department of Public Works and the state. The
plats shall be recorded with the Clerk of the Circuit Court. An unrecorded plat is not a valid basis
for site improvements or other commitments which depend on its characteristics.
A. A final subdivision plan shall be required for all residential land subdivisions resulting in
the creation of five or more lots, or for any residential subdivision where public improvements are
proposed.
B. A final site plan shall be required for all projects and/or land disturbing activities not
involving a residential subdivision, which propose construction, reconstruction, alteration, or
change of use where the project will cumulatively disturb more than two thousand five hundred
(2,500) square feet (232.26 square meters) of land. Any revisions to a valid approved final site
plan shall be processed and approved in accordance with Section 4.04.6.
6
April 2000
C. Final plats will be required for all subdivisions, resubdivisions, and consolidations of
parcels, delineation of vacation of easements, or right-of-way dedications where a legal
description is required. All required plats shall be submitted as part of the first cycle review
submission along with the final site or subdivision plans.
When the owner of several undersized existing nonconforming lots wants to consolidate
those parcels into one parcel for the construction of, or addition to an owner-occupied
single-family residence or accessory structure, a final plat will not be required. The consolidation
will only require the review and approval of a deed of consolidation.
4.03.4 Minor Site Plans. This plan type may be submitted when the proposed improvements are
being requested to a site on which the County either has not previously approved a site plan, or
on which there is an existing approved plan that has been closed. In addition, the improvements
must be minor in nature and generally (1) not change either the internal or external traffic flow
patterns; (2) not increase the number of dwelling units; (3) not increase the nonresidential building
size by more than five thousand (5,000) square feet (464.52 square meters), or seventy-five
percent (75%) of the gross building area, whichever is less; (4) not encroach into a resource
protection area; and (5) generally, the proposed disturbed area should not exceed five thousand
(5,000) square feet (464.62 square meters). This plan type includes one (1) waiver request
without additional fees. Any additional waiver requests will require the appropriate waiver fee.
4.03.5 Administrative Review Plans. This plan type may be submitted, following approval of
such a request by the Office of Planning, when the proposed improvements are to a previously
approved unclosed plan and/or constitute minor development such as temporary activities,
parking lot alterations, landscaping changes, storage tank replacement, etc., which doesn't
necessitate the formal submission of a full site plan.
Administrative reviews shall not generally include (1) redesign of infrastructure that
requires the certification of computations by registered professionals; (2) significant revisions to
the internal or external traffic patterns; (3) changes to the number of buildings, units and/or lots;
or (4) increases to the amount of impervious area.
4.03.6. Erosion and Sediment Control Plan (separate). This plan type is required for all land
disturbing activities, cumulatively exceeding two thousand five hundred (2,500) square feet
(232.26 square meters), which would not otherwise necessitate submission of either a final
subdivision or site plan. See Section 750.05 of the Design and Construction Standards Manual
for exemptions.
4.03.7 Comprehensive Review. For any of the above-cited major plan types, every effort
should be made to incorporate all additional studies and analyses required by the DCSM (i.e.,
preservation area site assessment, floodplain study, water quality impact assessment, etc.) into the
major plan application. This will permit a comprehensive review of the facts and approval of the
application.
This incorporation of multiple plan types is not meant to alter or reduce review fees. The
overall review fee will still be made up of its individual parts.
7
April 2000
4.03.8. Nonresidential Preconstruction Plan. Upon application to and subsequent initiation by
the director of Planning and the director of Economic Development, this plan type may be
submitted for the purpose of creating pad-ready sites in areas specifically zoned and intended for
office and/or targeted industry uses. In recommending this plan type, the director of Planning
may require landscaping, buffering and/or other improvements, as deemed appropriate. Upon
approval, the plan will remain valid for a period of six (6) months, unless a longer validity period
has been established by the director of Planning.
4.04. Application Review Process.
4.04.1. Sketch Plan Process.
STEP #1
SKETCH PLAN PRESUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Applicant submits plan to
OIT/Information Resources
Management Division; application
name approval, GPIN identification,
project number
N/A N/A Applicant;
OIT/Information
Resources Management
Division
NOTES:
With the advent of the land information system (LIS), all first-time application submissions must
be processed by the OIT/Information Resources Management Division prior to submittal to the
Division of Development Services. The purpose is to identify the existing parcel GPIN(s)
associated with the application, assign a project number, and approve the project name.
8
April 2000
STEP #2
SKETCH PLAN SUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Applicant submits plan to
Development Services
1 day 1 day Applicant; Development
Services
NOTES:
(1) The applicant should submit a complete application package, available at the
Development Services counter, including one copy of the sketch plan, appropriate quality control
checklist(s) development control form, fee calculation sheet, and fee check. Failure to do so will
result in rejection for acceptance and subsequent delay.
(2) If applicable, the applicant should include any requests for concurrent processing in the
application package.
(3) All process times (days) shown are calendar days.
9
April 2000
STEP #3
SKETCH PLAN QUALITY CONTROL REVIEW
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Quality control review,
create file/assign number;
assign project review team
3 days 4 days Development Services
NOTES:
(1) The submission is checked for completeness based upon the minimum submission
requirements cited on the appropriate quality control checklist(s) obtainable at the Development
Services counter. The applicant's fee calculation is checked for accuracy, and the approved
amount established. If the submitted fee is less than the approved fee by twenty percent (20%) or
more, the application is rejected. The submission is either accepted for processing or rejected. If
the application is accepted, a file is established with the preassignment project tracking number.
The applicant is so notified and told to submit the appropriate number of plans. The site/project is
also researched for prior applications/approvals/submittals (rezoning, SUP, site plan, etc.) and
those file numbers are noted on the new file. Review agencies are selected as appropriate,
depending on the type of application. In general, the selection is based upon the type of plan,
project size, and the type of improvements proposed. For sketch plans, this will usually only
include the Department of Public Works.
(2) If rejected, the submission is returned to the applicant, along with a list of deficiencies.
(3) A case manager and plan review team is assigned to coordinate the review and processing
of the application.
10
April 2000
STEP #4
SKETCH PLAN DISTRIBUTION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Development Services distributes
plan to review agencies; application
data entered into LIS
2 days 2 days Development Services
NOTES:
The application is distributed to the review agencies selected during the quality control review.
All the necessary project/submission data is entered into LIS, the computerized project tracking
system.
STEP #5
SKETCH PLAN REVIEW AND COMMENT
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Review agency analysis is undertaken
and results delivered to Development
Services; project review team
meeting held to consolidate all
review comments
6 days 12 days Development Services
and Public Works
Consolidation of comments by Public
Works
2 days 14 days Public Works
Summary letter issued 5 days 19 days Development Services
case manager
NOTES:
(1) The plan analysis by the review agencies will have three separate but interrelated
objectives. Objective one is to provide an analysis and comment on the application's consistency
with the comprehensive plan and with any approved proffers and/or SUP conditions. Objective
two is to conduct the technical review for compliance with the Zoning Ordinance and DCSM.
Objective three is to identify and list potential issues that must be addressed at subsequent levels
of plan submittal and review.
11
April 2000
(2) All engineering-related comments prepared by the Department of Public Works, and any
additional agencies that have reviewed the plan, will be forwarded directly to Public Works,
Watershed Management Division. Subsequently, one consolidated and internally consistent
engineering review letter will be forwarded to the Division of Development Services within the
time frame established for the completion of this step.
Review agency letters should be divided into engineering and nonengineering sections.
Although the original is sent to Public Works, a copy is also sent to Development Services for the
official file.
(3) Development Services will, during this step, perform the Zoning Ordinance review and
administrative and nonengineering review of the DCSM.
(4) The Watershed Management Division of the Department of Public Works will consolidate
all the technical engineering comments and transmit one consolidated review to Development
Services.
(5) If necessary, a project review team meeting will be held to discuss and consolidate all
review comments into one internally consistent summary letter. The summary letter will be
written and issued by the Development Services project review team chairman.
(6) The sketch plan summary letter conference date will be established by the project review
team chairman, and it will be cited in the summary letter. The date will be within fourteen (14)
calendar days of the issuance of the summary letter.
12
April 2000
STEP #6
SKETCH PLAN SUMMARY LETTER CONFERENCE
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Schedule and hold conference 14 days 33 days Development Services
(appropriate project
review team chairman);
Public Works;
OIT/Information
Resources Management
Division; applicant
NOTES:
(1) The applicant shall submit a response letter to the case manager addressing all comments
contained in the summary letter three (3) days prior to the sketch plan summary letter conference.
(2) This meeting is held to discuss the salient aspects of the project, including the design
concept, size, access, layout, extent, location and degree of the improvements necessary or
proposed, etc.
(a) If agreement and consensus is reached by all parties, the attendees shall mark any
agreed upon revisions and resolutions on a copy of the sketch plan and response letter and sign
and date the revised plan. This will form the general basis for the design of the final plans.
(b) If consensus is not reached, the file will be so noted with the unresolved items and
the applicant and design professional will proceed with the final plan with the understanding that
the unresolved issues may delay the subsequent approval process.
(c) The sketch plan summary letter conference shall be attended by the members of the
project review team, any additional appropriate review agencies, the design professional, and/or
the applicant.
(3) The results of the sketch plan summary letter conference shall remain in effect for twelve
(12) months from the date of the meeting. If, during that period, no final plans are accepted for
review and being diligently pursued to approval, or if final plans were approved and diligent
pursuit is not demonstrated by bonding the plans and recording the plats within the necessary time
frames, the sketch plan shall be void. In such instances, no final plans shall be accepted for review
until a new sketch plan has been submitted and reviewed, or the previous sketch plan has been
revalidated for an additional twelve- (12) month period by the director of Planning, upon
demonstration by the applicant that such sketch plan meets all current standards.
13
April 2000
(a) Additionally, major changes, corrections or adjustments to the sketch plan affecting
project size, intensity, density, or internal or external traffic flow shall require submission of a new
sketch plan.
(b) Consensus on a sketch plan does not constitute an approval of the final plans and plats,
nor should the approval be considered a valid basis for the construction of site improvements.
4.04.2 Preliminary Residential Site Plan Process.
STEP #1
PRESUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Applicant submits plan to
OIT/Information Resources
Management Division; application
name approval, GPIN identification,
project number
N/A N/A Applicant;
OIT/Information
Resources Management
Division
NOTES:
With the advent of the land information system (LIS), all first-time application submissions must
be processed by the OIT/Information Resources Management Division, prior to submittal to
Development Services. The purpose is to identify the existing parcel GPIN(s) associated with the
application, assign a project number, and approve the project name.
14
April 2000
STEP #2
PRELIMINARY RESIDENTIAL SITE PLAN SUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Applicant submits plan to
Development Services
1 day 1 day Applicant; Development
Services
NOTES:
(1) The applicant should submit a complete application package, the requirements of which
are available at the Development Services counter, including one copy of the preliminary site plan,
appropriate quality control checklist(s) development control form, fee calculation sheet, and fee
check. Failure to do so will result in a rejection of the application and subsequent delays.
(2) If applicable, the applicant shall include any requests for waiver or concurrent processing
of the submission with a rezoning or special use permit.
(3) All process times (days) shown are calendar days.
15
April 2000
STEP #3
PRELIMINARY RESIDENTIAL SITE PLAN QUALITY CONTROL REVIEW
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Quality control review, create file;
assign project review team
3 days 4 days Development Services
NOTES:
(1) The submission is checked for completeness based upon the minimum submission
requirements cited on the appropriate quality control checklist(s) obtainable at the Development
Services counter. The applicant's fee calculation is checked for accuracy, and the approved
amount established. If the submitted fee is less than the approved fee by twenty percent (20%),
the application is rejected. The submission is either accepted for processing or rejected. If the
application is accepted, a file is established with the preassigned project tracking number. The
applicant is so notified and told to submit the appropriate number of plans. The site/project is
also researched for prior applications/approvals/submittals (rezoning, SUP, site plan, etc.) and
those file numbers are noted on the new file. Review agencies are selected as appropriate,
depending on the type of application. In general, the selection is based upon the type of plan,
project size, and the type of improvements proposed. For preliminary site plans, this will usually
only include the Department of Public Works, PWC Service Authority, VDOT, Health
Department, and the OIT/Information Resources Management Division.
(2) If rejected, the submission is returned to the applicant, along with a list of deficiencies.
(3) A case manager and plan review team is assigned to coordinate the review and processing
of the application.
16
April 2000
STEP #4
PRELIMINARY RESIDENTIAL SITE PLAN DISTRIBUTION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Development Services distributes
plan to review agencies; application
data entered into LIS
2 days 6 days Development Services
NOTES:
The application is distributed to the review agencies selected during the quality control review.
All the necessary project/submission data is entered into LIS, the computerized project tracking
system.
17
April 2000
STEP #5
PRELIMINARY RESIDENTIAL SITE PLAN REVIEW AND COMMENT
First Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Review agency analysis is undertaken
and results delivered to Development
Services; project review team
meeting held to consolidate all
review comments
9 days 15 days Development Services;
Public Works;
OIT/Information
Resources Management
Division; Health, and
PWC Service Authority
Consolidation of engineering
comments by Public Works
3 days 18 days Public Works
Summary letter issued 4 days 22 days Development Services
NOTES:
(1) The County shall review the practicality of the preliminary site plan and its general design.
Attention shall be given to the following: location and width of streets and travelways,
orientation, coordination, compatibility, and size of structures, the general relationship of the
project to the topography of the land, feasibility of water supply and sewage disposal, general
handling of site drainage, density and lot/unit arrangement, the future development of adjoining
lands as yet undeveloped, the relationship of adjoining developed lands, as well as potential
impacts to existing and future land uses in the area, and the requirements/guidelines of the
comprehensive plan, Zoning Ordinance, and subdivision ordinance.
Approval of a preliminary site plan does not constitute an approval of the final plan and
plats, nor should the approval be considered a valid basis for the construction of site
improvements.
(2) The case manager/project review team chairman, in order to coordinate the overall review
and processing of an application, shall be the focal point for all scheduling and shall be apprised of
all meetings between the applicant and review agency representatives designed to discuss major
issues. While the chairman may choose not to participate in a specific discussion, he/she should
have the opportunity to do so.
(3) The plan analysis by the review agencies will have three separate but interrelated
objectives. Objective one is to provide an analysis and comment on the application's consistency
with the comprehensive plan and with any approved proffers and/or SUP conditions. Objective
two is to conduct the technical review for compliance with the Zoning Ordinance and DCSM.
Objective three is to identify and list potential issues that must be addressed at subsequent levels
of plan submittal and review.
18
April 2000
(4) All engineering-related comments prepared by all commenting agencies (VDOT, PWC
Service Authority, OIT/Information Resources Management Division, Health Department) will be
forwarded directly to Public Works, Watershed Management Division. Subsequently, one
consolidated and internally consistent engineering review letter will be forwarded to Development
Services within the time frame established for the completion of this step. Simultaneously, Public
Works will refer nonengineering-related comments to Development Services for resolution.
Review agency letters should be divided into engineering and nonengineering sections.
Although the original is sent to Public Works, a copy is also sent to Development Services for the
official file.
(5) Development Services will during this step perform the Zoning Ordinance review and the
administrative and nonengineering review of the DCSM.
(6) The Watershed Management Division of the Department of Public Works will consolidate
all the technical engineering comments into one consolidated review and transmit it to
Development Services.
(7) The internally consistent first cycle summary letter will be issued by the Development
Services case manager. This letter will outline the plan deficiencies that must be addressed and
any additional comments, concerns and issues raised by the various review agencies.
(a) The date and time of the post summary letter conference will be cited in the summary
letter.
(b) The application resubmission date and the required number of plans to be
resubmitted will also be cited.
19
April 2000
STEP #6
PRELIMINARY RESIDENTIAL SITE PLAN
POST SUMMARY LETTER CONFERENCE
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Schedule and hold conference 20 days 42 days Development Services
(appropriate project
review team chairman;
Public Works;
OIT/Information
Resources Management
Division; VDOT; PWC
Service Authority; Health
Department; applicant)
NOTES:
(1) This meeting is held to discuss all relevant aspects of the project and attempt to resolve all
issues that were identified in the summary letter.
The conference is scheduled, coordinated and chaired by the project review team
chairman.
(2) The applicant shall submit a response letter, addressing all comments contained in the
summary letter, to the project review team chairman (case manager) three (3) days prior to the
post summary letter conference date.
(3) If all the comments raised in the summary letter are adequately addressed during the
conference, the case manager may immediately recommend the application for signature. A
signature summary letter will then be issued within four (4) business days of the conference.
(4) If all comments are not adequately addressed, the applicant will be instructed to make
revisions to the plan and resubmit the plans for a second review cycle.
20
April 2000
STEP #2.1
(If Necessary)
PRELIMINARY RESIDENTIAL SITE PLAN RESUBMISSION
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Revise initial application submission;
resubmit
45 days 87 days Applicant
NOTES:
(1) Based upon Step #6, the applicant will revise the application in conformance with the
summary letter and/or agreements reached during the post submission summary letter conference.
The revised application will be submitted to Development Services no later than the deadline cited
in the summary letter (i.e., 45 days from the issuance of the summary letter).
(2) All review comments contained in the first review cycle summary letter must either be
addressed via an application revision, or signed off by the approving authority (i.e., VDOT,
Service Authority, etc.) before the revised submission can be accepted for the second review
cycle.
21
April 2000
STEP #3.1
(If Necessary)
PRELIMINARY RESIDENTIAL SITE PLAN QUALITY CONTROL REVIEW
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Quality control review 3 days 90 days Development Services
NOTES:
(1) The resubmission, and the responses provided by the applicant, are checked for
completeness by the project's case manager, based upon the results of the first review cycle post
summary letter conference.
(a) If all comments and issues have been adequately addressed and/or approved by their
approving authority, the application will be immediately recommended for signature. The case
manager will issue a signature summary letter.
(b) If all comments have not been adequately addressed, the application will be
distributed to the various review agencies for the second review cycle.
(2) If major revisions have occurred to the plans as a result of either the prior review
comments, or a project redesign, the application shall revert to a new first review cycle time frame
(see Step #5).
22
April 2000
STEP #4.1
(If Necessary)
PRELIMINARY RESIDENTIAL SITE PLAN DISTRIBUTION
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Development Services distributes
plan to review agencies
1 day 91 days Development Services
NOTES:
The application is distributed to the review agencies that did not approve the first cycle plan, as
appropriate (Department of Public Works, PWC Service Authority, VDOT, Health Department,
and the OIT/Information Resources Management Division).
23
April 2000
STEP #5.1
(If Necessary)
PRELIMINARY RESIDENTIAL SITE PLAN REVIEW AND COMMENT
Second Review
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Review agency analysis is undertaken
and results delivered to Development
Services
6 days 97 days Development Services
Case Manager; Public
Works; VDOT;
OIT/Information
Resources Management
Division; Health
Department; Service
Authority; as appropriate
Consolidation of engineering
comments by Public Works
2 days 99 days Public Works
Summary letter issued 5 days 104 days case manager
NOTES:
All review comments will be consolidated into one internally consistent second cycle summary
letter. The letter will be written and issued by the Development Services case manager.
(a) If the application is not approved, following the receipt of the review agency
comments, the summary letter will cite the date and time of the post summary letter conference.
(b) If the application is approved, a signature summary letter will be issued, rather than a
standard second cycle summary letter. It will outline the necessary minor application revisions
required.
24
April 2000
STEP #6.1
(If Necessary)
PRELIMINARY RESIDENTIAL SITE PLAN
POST SUMMARY LETTER CONFERENCE
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Schedule and hold conference 14 days 118 days Development Services
(appropriate project
review team chairman);
appropriate review
agencies; applicant
NOTES:
(1) The meeting is held to discuss all relevant aspects of the project and attempt to resolve all
issues that were identified in the second cycle summary letter.
(2) The applicant shall submit a response letter, addressing all comments contained in the
second cycle summary letter to the project review team chairman (case manager) three (3) days
prior to the conference.
(3) If all the comments raised in the second cycle summary letter are adequately addressed
during the conference, and the application is approved, the case manager will immediately
recommend the application for signature. A signature summary letter is issued within four (4)
days of the conference.
(4) If all the comments raised are not adequately addressed, or if solutions cannot be agreed
upon, the application shall be forwarded to the project resolution committee by the case manager
to resolve the remaining issues. The project resolution committee is a management level
committee composed of the chief of Development Services and the chiefs of the Department of
Public Works Transportation and Watershed Management divisions. The committee shall hold a
meeting with the applicant and the project review team to discuss the remaining issues and
determine the final recommendation to either approve or deny the application.
(a) If the committee recommends approval, the case manager shall issue a signature
summary letter.
(b) If the committee cannot resolve all the outstanding issues, they shall recommend
denial of the application to the director of Planning.
(c) The committee shall schedule its meeting to discuss the project within fourteen (14)
business days of the date of the second cycle post summary letter conference.
25
April 2000
STEP #7
PRELIMINARY RESIDENTIAL SITE PLAN CURSORY SIGNATURE SUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Review application and submit for
cursory signature review
30 days 148 days Applicant
NOTES:
Based upon either Step #6 or Step #6.1, the applicant will revise the application in conformance
with the signature summary letter. Five (5) copies of the revised application shall be submitted to
Development Services no later than the deadline cited in the signature summary letter.
STEP #8
PRELIMINARY RESIDENTIAL SITE PLAN CURSORY SIGNATURE REVIEW
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Conduct cursory review; write and
issue cursory review letter
4 days 152 days Development Services;
Public Works; Service
Authority;
OIT/Information
Resources Management
Division
NOTES:
The application will undergo a cursory review by the project review team, OIT/Information
Resources Management Division, and the Service Authority. A cursory review letter is issued by
the case manager, citing any minor revisions necessary to be made to the application prior to the
plans being signed.
26
April 2000
STEP #9
PRELIMINARY RESIDENTIAL SITE PLAN SIGNATURE SUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Revise application; submit for
approval and signature
30 days 182 days Applicant
NOTES:
The application is revised based upon the cursory review letter and the proper number of copies
are submitted for approval and signature to Development Services.
STEP #10
PRELIMINARY RESIDENTIAL SITE PLAN APPROVAL AND SIGNATURE
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Sign application 4 days 186 days Development Services
NOTES:
Upon submittal, the application (preliminary site plan) will be reviewed by the Development
Services case manager for completeness as outlined in the cursory review letter. If the application
is complete, the application will be stamped and signed by the chief of Development Services.
27
April 2000
4.04.3. Preliminary Residential Subdivision Plan Process.
STEP #1
PRESUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Applicant submits plan to the
OIT/Information Resources
Management Division; application
name approval, GPIN identification,
project number
N/A N/A Applicant;
OIT/Information
Resources Management
Division
NOTES:
With the advent of the land information system (LIS), all first-time application submissions must
be processed by the OIT/Information Resources Management Division prior to submittal to
Development Services. The purpose is to identify the existing parcel GPIN(s) associated with the
application, assign a project number, and approve the project name.
STEP #2
PRELIMINARY RESIDENTIAL SUBDIVISION PLAN SUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Applicant submits plan to
Development Services
1 day 1 day Applicant; Development
Services
NOTES:
(1) The applicant should submit a complete application package, the requirements of which
are available at the Development Services counter, including one (1) copy of the preliminary
subdivision plan, appropriate quality control checklist(s), development control form, fee
calculation sheet, and fee check. Failure to do so will result in a rejection of the application and
subsequent delays.
(2) If applicable, the applicant should include any requests for waivers or concurrent
processing of the submission with a rezoning or special use permit.
(3) All process times (days) shown are calendar days.
28
April 2000
STEP #3
PRELIMINARY RESIDENTIAL SUBDIVISION QUALITY CONTROL REVIEW
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Quality control review; create file/
assign number; assign project review
team
3 days 4 days Development Services
NOTES:
(1) The submission is checked for completeness based upon the minimum submission
requirements cited on the appropriate quality control checklist(s) obtainable at the Development
Services counter. The applicant's fee calculation is checked for accuracy and the approved
amount established. If the submitted fee is less than the approved fee by twenty percent (20%) or
more, the application is rejected. The submission is either accepted for processing or rejected. If
the application is accepted, a file is established with the preassigned project tracking number. The
applicant is so notified and told to submit the appropriate number of plans. The site/project is
also researched for prior applications/approvals/submittals (rezoning, SUP, site plan, etc.), and
those file numbers are noted on the new file. Review agencies are selected, as appropriate,
depending on the type of application. In general, the selection is based upon the type of plan,
project size, and the type of improvements proposed. For preliminary subdivisions, this will
usually only include the Department of Public Works, OIT/Information Resources Management
Division, PWC Service Authority, VDOT, and the Health Department.
(2) If rejected, the submission is returned to the applicant, along with a list of deficiencies.
(3) A case manager and plan review team is assigned to coordinate the review and processing
of the application.
29
April 2000
STEP #4
PRELIMINARY RESIDENTIAL SUBDIVISION PLAN DISTRIBUTION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Development Services distributes
plan to review agencies; application
data entered into LIS
2 days 6 days Development Services
NOTES:
The application is distributed to the review agencies selected during the quality control review.
All the necessary project/submission data is entered into LIS, the computerized project tracking
system.
30
April 2000
STEP #5
PRELIMINARY RESIDENTIAL SUBDIVISION REVIEW AND COMMENT
First Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Review agency analysis is undertaken
and results delivered to Development
Services; project review team meeting
held to consolidate all review
comments
9 days 15 days Development Services; Public
Works; OIT/Information
Resources Management
Division; Health Department
and Service Authority
Consolidation of engineering
comments by Public Works
3 days 18 days Public Works
Summary letter issued 4 days 22 days Development Services case
manager
NOTES:
(1) The County shall review the practicality of the preliminary subdivision plan and its general
design. Attention shall be given to the following: location and width of streets and travelways,
orientation, coordination, compatibility, and size of structures, the general relationship of the
project to the topography of the land, feasibility of water supply and sewage disposal, general
handling of site drainage, lot sizes and arrangement, the future development of adjoining lands as
yet undeveloped, the relationship adjoining developed lands, as well as potential impacts to
existing and future land uses in the area, and the requirements/guidelines of the comprehensive
plan, Zoning Ordinance, and subdivision ordinance.
Approval of a preliminary subdivision plan does not constitute an approval of the final
plan and plats, nor should the approval be considered a valid basis for the construction of site
improvements.
(2) The case manager/project review team chairman, in order to coordinate the overall review
and processing of an application, shall be the focal point for all scheduling and shall be apprised of
all meetings between the applicant and review agency representatives designed to discuss major
issues. While the chairman may choose not to participate in a specific discussion, he/she should
have the opportunity to do so.
31
April 2000
(3) The plan analysis by the review agencies will have three separate but interrelated
objectives. Objective one is to provide an analysis and comment on the application's consistency
with the comprehensive plan and with any approved proffers and/or SUP conditions. Objective
two is to conduct the technical review for compliance with the Zoning Ordinance and DCSM.
Objective three is to identify and list potential issues that must be addressed at subsequent levels
of plan submittal and review.
(4) All engineering-related comments prepared by all commenting agencies (VDOT, PWC
Service Authority, OIT/Information Resources Management Division, Health Department) will be
forwarded directly to Public Works, Watershed Management Division. Subsequently, one
consolidated and internally consistent engineering review letter will be forwarded to Development
Services within the time frame established for the completion of this step. Simultaneously, Public
Works will refer all nonengineering-related comments to Development Services for resolution.
Review agency letters shall be divided into engineering and nonengineering sections.
Although the original is sent to Public Works, a copy is also sent to Development Services for the
official file.
(5) Development Services will, during this step, perform the Zoning Ordinance review, the
administrative and nonengineering review of the DCSM.
(6) The Watershed Management Division of the Department of Public Works will consolidate
all the technical engineering comments into one consolidated review and transmit it to
Development Services.
(7) The internally consistent first cycle summary letter will be issued by the Development
Services case manager. This summary letter will outline the plan deficiencies that must be
addressed and any additional comments, concerns and issues raised by the various review
agencies.
(a) The date and time of the post summary letter conference will be cited in the summary
letter.
(b) The application resubmission date, and the required number of plans to be
resubmitted will also be cited.
32
April 2000
STEP #6
PRELIMINARY RESIDENTIAL SUBDIVISION
POST SUMMARY LETTER CONFERENCE
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Schedule and hold conference 20 days 42 days Development Services
(appropriate project review
team chairman); Public
Works; OIT/Information
Resources Management
Division; VDOT; Service
Authority; Health
Department; applicant
NOTES:
(1) This meeting is held to discuss all relevant aspects of the project and attempt to resolve all
issues that were identified in the summary letter. The conference is scheduled, coordinated and
chaired by the project review team chairman.
(2) The applicant shall submit a response letter addressing all comments contained in the
summary letter to the project review team chairman (case manager) three (3) days prior to the
post summary letter conference date.
(3) If all the comments raised in the summary letter are adequately addressed during the
conference, the case manager may immediately recommend the application for signature. A
signature summary letter will then be issued within five (5) days of the conference.
(4) If all comments are adequately addressed, the applicant will be instructed to make
revisions to the plan and resubmit the plans for a second review cycle.
33
April 2000
STEP #2.1
PRELIMINARY RESIDENTIAL SUBDIVISION PLAN RESUBMISSION
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Review initial application submission;
resubmit
45 days 87 days Applicant
NOTES:
(1) Based upon Step #6, the applicant will review the application in conformance with the
summary letter and/or agreements reached during the post submission summary letter conference.
The revised application will be submitted to Development Services no later than the deadline cited
in the summary letter (i.e., forty-five [45] days from the issuance of the summary letter).
(2) All review comments contained in the first review cycle summary letter must either be
addressed via an application revision, or signed off by the approving authority (i.e., VDOT,
Service Authority, etc.) before the revised submission can be accepted for second review cycle.
34
April 2000
STEP #3.1
(If Necessary)
PRELIMINARY RESIDENTIAL SUBDIVISION QUALITY CONTROL REVIEW
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Quality control review 3 days 90 days Development Services
NOTES:
(1) The resubmission and the responses provided by the applicant are checked for
completeness based upon the results of the first review cycle post summary letter conference.
(a) If all comments and issues have been adequately addressed and/or approved by their
approving authority, the application will be immediately recommended for signature. The case
manager will issue a signature summary letter.
(b) If all comments have not been adequately addressed, the application will be
distributed to the various review agencies for second review cycle.
(2) If major revisions have occurred to the plans as a result of either the prior review
comments or a project redesign, the application shall revert to a new first review cycle time frame
(see Step #5).
STEP #4.1
(If Necessary)
PRELIMINARY RESIDENTIAL SUBDIVISION PLAN DISTRIBUTION
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Development Services distributes
plan to review agencies
1 day 91 days Development Services
NOTES:
The application is distributed to the review agencies that did not approve the first cycle plan, as
appropriate (Department of Public Works, the Service Authority, VDOT, Health Department, and
the OIT/Information Resources Management Division).
35
April 2000
STEP #5.1
(If Necessary)
PRELIMINARY RESIDENTIAL SUBDIVISION PLAN REVIEW AND COMMENT
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Review agency analysis is undertaken
and results delivered to Development
Services
6 days 97 days Development Services
case manager, Public
Works; VDOT; Health
Department; Service
Authority, as appropriate
Consolidation of engineering
comments by Public Works
2 days 99 days Public Works
Summary letter issued 5 days 104 days Case Manager
NOTES:
All review comments will be consolidated into one internally consistent second cycle summary
letter. The summary letter will be written and issued by the Development Services case manager.
(a) If the application is not approved in its present form, following the receipt of the review
agency comments, the summary letter will cite the date and time of the post summary letter
conference.
(b) If the application is approved, a signature summary letter will be issued, rather than a
standard second cycle summary letter. It will outline the necessary minor application revisions
required.
36
April 2000
STEP #6.1
(If Necessary)
PRELIMINARY RESIDENTIAL SUBDIVISION
POST SUMMARY LETTER CONFERENCE
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Schedule and hold conference 14 days 118 days Development Services
(appropriate project
review team chairman)
appropriate review
agencies; applicant
NOTES:
(1) The meeting is held to discuss all relevant aspects of the project and attempt to resolve all
issues that were identified in the second cycle summary letter.
(2) The applicant shall submit a response letter, addressing all comments contained in the
second cycle summary letter, to the project review team chairman (case manager) three (3) days
prior to the conference.
(3) If all the comments raised in the second cycle summary letter are adequately addressed
during the conference, and the application is approved, the case manager will immediately
recommend the application for signature. A signature summary letter is issued within four (4)
days of the conference.
(4) If all the comments raised are not adequately addressed, or if solutions cannot be agreed
upon, the application shall be forwarded to the project resolution committee by the case manager
to resolve the remaining issues. The project resolution committee is a management level
committee composed of the chief of Development Services and the chiefs of the Department of
Public Works Transportation and Watershed Management divisions. The committee shall hold a
meeting with the applicant and the project review team to discuss the remaining issues and
determine the final recommendation to the Planning Commission to either approve or deny the
application.
(a) If the committee recommends approval, the case manager shall issue a signature
summary letter.
37
April 2000
(b) If the committee cannot resolve all the outstanding issues, they shall recommend
denial of the application to the Planning Commission.
(c) The committee shall schedule its meeting to discuss the project within fourteen (14)
business days of the date of the second cycle post summary letter conference.
STEP #7
PRELIMINARY RESIDENTIAL SUBDIVISION
CURSORY SIGNATURE SUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Review application and submit for
cursory signature review
30 days 148 days Applicant
NOTES:
(1) Based upon either Step #6 or Step #6.1, the applicant shall revise the application in
conformance with the signature summary letter. Five (5) copies of the revised application shall be
submitted to Development Services no later than the deadline cited in the signature summary
letter.
38
April 2000
STEP #8
PRELIMINARY RESIDENTIAL SUBDIVISION CURSORY SIGNATURE REVIEW
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Conduct cursory review; write and
issue cursory review letter
4 days 152 days Development Services;
Public Works; Service
Authority;
OIT/Information
Resources Management
Division
NOTES:
The application will undergo a cursory review by the project review team, OIT/Information
Resources Management Division and the Service Authority. A cursory review letter is issued by
the case manager, citing any minor revisions necessary to be made to the application prior to the
plans being sent to the Planning Commission for action.
39
April 2000
STEP #9
PRELIMINARY RESIDENTIAL SUBDIVISION
PLANNING COMMISSION SUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Revise application; submit for action;
schedule Planning Commission
meeting; write and issue staff report
30 days 182 days Applicant
NOTES:
(1) The application is revised, based upon the cursory review letter, and the proper number of
copies are resubmitted for Planning Commission action to Development Services.
(2) A Planning Commission meeting date is scheduled for the first available date at this time.
The applicant will be notified of this date. The date is determined by the Planning Commission
chairman.
(3) A staff report will be written by the case manager. It must be transmitted to the Planning
Commission, along with corrected copies of the preliminary residential subdivision plans, at least
fourteen (14) days prior to the meeting date.
(a) The staff report shall recommend either approval or denial of the application.
STEP #10
PRELIMINARY RESIDENTIAL SUBDIVISION PLANNING COMMISSION MEETING
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Application is approved/denied N/A N/A Development Services
case manager; Planning
Commission
NOTES:
(1) If the application is approved by the Planning Commission, the plans are stamped and signed
by the chief of Development Services. If the application is denied by the Planning Commission,
the decision is final and the application file is closed.
40
April 2000
4.04.3.1. Term of Validity: Preliminary Residential Subdivision and Site Plans.
A. Preliminary Residential Subdivision and Site Plans. All preliminary residential plan
approvals are valid for two and one-half (2 1/2) years from their date of approval. If, during that
period, either (1) no final plans are approved, (2) no final plans are submitted for review and being
diligently pursued to approval, or (3) if final plans were approved and continued diligent pursuit is
not demonstrated by bonding the plans and recording the plats, the preliminary residential plans
shall become void after its approval period expires. If a preliminary residential plan approval
expires, no additional action shall be taken on the plan without the submission of new plans and
payment of all applicable fees. If, during the term of validity, a final plan for either the entire
project, or one or more phases of a multiphased project, is approved and recorded, the
preliminary plan will then be valid for five (5) years from the date of recordation of the plat(s)
associated with the approved final plan.
B. Preliminary Residential Plan Revisions. Any revisions to a valid, approved, preliminary
residential plan, or any remaining portion of a valid preliminary residential plan, which
(a) increases the density (units or lots of the project), (b) effects the approved land use(s), or
(c) effects zoning issues, shall be processed and approved in accordance with either Section
4.04.2 or Section 4.04.3 above, whichever is applicable. In instances where the revisions do not
effect the above-stated items, the director of Planning, or the designee, shall have the authority to
approve the revisions administratively.
C. Revalidation of Approved Preliminary Residential Plans. Following the end of the initial
two and one-half (2 1/2) year validity period or the subsequent five- (5) year validity period of a
preliminary residential plan, for those phases of the project that have either not been completed,
are under construction, or have been accepted for final approval, the County will require that the
remaining phase(s) undergo a cursory review to reestablish conformity with all current
regulations.
(1) If the cursory review indicates the preliminary residential plan remains in conformity,
its approval will be revalidated for an additional two and one-half (2 1/2) year period.
(2) If the cursory review indicates the preliminary residential plan is not in conformity
with various regulations, those areas of nonconformity shall be enumerated in written form to the
applicant and design professional. In such instances, no additional final plans will be accepted for
review until the preliminary residential plan is brought into conformance. Any revisions necessary
to the preliminary residential plan shall be processed and approved in accordance with either
Section 4.04.2 or Section 4.04.3 above, whichever is applicable.
41
April 2000
4.04.4 Final Site and Subdivision Plan and Plat Process.
STEP #1
PRESUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Applicant submits plan to
OIT/Information Resources
Management Division; application
name approval, GPIN identification,
project number
N/A N/A Applicant;
OIT/Information
Resources Management
Division
NOTES:
With the advent of the land information system (LIS), all first-time application submissions must
be processed by the OIT/Information Resources Management Division prior to submittal to
Development Services. The purpose is to identify the existing parcel GPIN(s) associated with the
application, assign a project number, and approve the project name.
42
April 2000
STEP #2
FINAL PLAN AND PLAT SUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Applicant submits plan to
Development Services
1 day 1 day Applicant; Development
Services
NOTES:
(1) The applicant should submit a complete application package, available at the
Development Services counter, including one copy of the site plan, easement and/or subdivision
plat(s) as appropriate, appropriate quality control checklists(s), development control form, fee
calculation sheet, fee check, and unit price list. Failure to do so will result in rejection for
acceptance and subsequent delays. All necessary plats must be submitted at this time or the
application will be rejected.
(2) If applicable, the applicant should include any requests for concurrent processing of the
submission with a rezoning or special use permit request.
(3) If applicable, any necessary or desired waiver requests should have previously been
submitted and acted upon prior to the application submittal.
(4) All process times (days) shown are calendar days.
43
April 2000
STEP #3
FINAL PLAN AND PLAT QUALITY CONTROL REVIEW
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Quality control review; create
file/assign number, assign project
review team
3 days
2 days*
2 days**
4 days
3 days*
3 days**
Development Services
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
(1) The submission is checked for completeness, based upon the minimum submission
requirements cited on the appropriate quality control checklist(s) obtainable at the Development
Services counter. County staff will also review the applicant's fee calculation for accuracy and
establishment of an approved amount. If the submitted fee is less than the approved fee by twenty
percent (20%) or more, the application is rejected. As a result of this quality control review, the
submission is either accepted for processing or rejected. If the application is accepted, a file is
established with the preassigned project tracking number. If accepted, the site/project is
researched for prior applications/ approvals/submittals (rezoning, SUP, site plan, etc.) and those
file numbers are noted on the new file. Review agencies are selected, as appropriate, depending
on the type of application. In general, the selection has traditionally been based upon the type of
plan, project size, and the type of improvements proposed. For final plans, this could include the
Department of Public Works, PWC Service Authority, VDOT, Health Department, Fire and
Rescue, PWC Park Authority, PWC School Administration, Dale Service Corporation, Virginia
American Water Company, Virginia State Health Department, and the OIT/Information
Resources Management Division.
(2) If rejected, the submission is returned to the applicant, along with a list of deficiencies.
(3) A case manager and plan review team is assigned to coordinate the review and processing
of the application.
(4) In instances where either a preliminary residential plan or sketch plan was required, final
plans and plats shall not be accepted for review until the preliminary residential or sketch plan has
been approved.
(5) All final plans and plats shall be designed in conformance with the current standards and
regulations in effect at the time of their first cycle submission, except as otherwise provided under
duly adopted vesting guidelines.
44
April 2000
STEP #4
FINAL PLAN AND PLAT DISTRIBUTION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Development Services distributes
plan to review agencies; application
data entered into LIS
1 day
1 day*
1 day**
5 days
4 days*
4 days**
Development Services
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
The application is distributed to the review agencies selected during the quality control review.
All the necessary projects/submission data is entered into LIS, the computerized project tracking
system.
45
April 2000
STEP #5
FINAL PLAN AND PLAT REVIEW AND COMMENT
First Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Review agency analysis is undertaken
and results delivered to the
Development Services; project
review team meeting held to
consolidate all review comments
23 days
10 days*
14 days**
28 days
14 days*
18 days**
Development Services;
Public Works; VDOT;
OIT/Information
Resources Management
Division; Health
Department; Service
Authority; School
Administration; Fire &
Rescue; Dale Service
Corp.; Virginia American
Water Co.; Park
Authority; and Virginia
State Health Department
Consolidation of engineering
comments by Public Works
4 days
3 days*
3 days**
32 days
17 days*
21 days**
Public Works
Summary letter issued 5 days
4 days*
4 days**
37 days
21 days*
25 days**
Development Services
case manager
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
(1) The case manager/project review team chairman, in order to coordinate the overall review
and processing of an application, shall be the focal point for all scheduling and shall be apprised of
all meetings between the applicant and review agency representatives, to discuss major issues.
While the chairman may choose not to participate in a specific discussion, he/she shall have the
opportunity to do so.
(2) The plan analysis by the review agencies will have two separate but interrelated
objectives. Objective one is to provide an analysis and comment on the application's consistency
with any approved proffers and/or SUP conditions or provisional use permit (PUP) conditions.
Objective two is to conduct the technical review for compliance with the Zoning Ordinance and
DCSM.
46
April 2000
(3) All engineering-related comments prepared by all agencies commenting on this subject
(VDOT, Service Authority, OIT/Information Resources Management Division, Health
Department, Fire and Rescue, Dale Service Corp., Virginia American Water Co., and Virginia
State Health Department) will be forwarded directly to Public Works, Watershed Management
Division. Subsequently, one consolidated and internally consistent engineering review letter will
be forwarded to Development Services within the time frame established for the completion of
this step.
Review agency letters shall be divided into engineering and nonengineering sections.
Although the original is sent to Public Works, a copy is also sent to Development Services for the
official file.
(4) Development Services will perform the Zoning Ordinance, administrative and
nonengineering reviews of the DCSM.
(5) The Watershed Management Division of the Department of Public Works will consolidate
all the technical engineering comments into one consolidated review and transmit it to
Development Services.
(6) A project review team meeting will be held to discuss and consolidate all review
comments into one internally consistent first review cycle summary letter. The summary letter
will be written and issued by the Development Services chief within five (5) days of the receipt of
the Department of Public Works consolidated review letter. The summary letter will outline the
plan deficiencies that must be addressed and any additional comments, concerns and issues raised
by the various review agencies.
(a) The date and time of the post summary letter conference will be cited in the summary
letter.
(b) The application resubmission date and the required number of plans and plats to be
resubmitted are also cited.
47
April 2000
STEP #6
FINAL PLAN AND PLAT POST SUMMARY LETTER CONFERENCE
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Schedule and hold conference;
discuss findings with applicant
20 days
15 days*
15 days**
57 days
36 days*
40 days**
Development Services
(appropriate project
review team); Public
Works; OIT/Information
Resources Management
Division; VDOT; Service
Authority; Health
Department; School
Administration; Park
Authority; Fire & Rescue
as appropriate; applicant
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
(1) The meeting is held to discuss all relevant aspects of the project and attempt to resolve all
issues that were identified in the summary letter. It is scheduled, coordinated and chaired by the
project review team chairman.
Prior to the meeting, the applicant should attempt to resolve any issues possible. Any
subsequent approvals by agencies shall be documented prior to or at the conference. All issues
will be considered unresolved until documented.
(2) The applicant shall submit a response letter, addressing all comments contained in the
summary letter, to the project review team chairman (case manager) three (3) days prior to the
post summary letter conference date.
(3) If all the comments raised in the summary letter are adequately addressed during the
conference, the case manager will immediately recommend the application for signature. A
signature summary letter is issued within four (4) days of the conference.
(4) If all the comments raised are not adequately addressed, the applicant will be instructed to
make revisions to the plan and resubmit the plans for a second review cycle.
48
April 2000
STEP #7
FINAL PLAN AND PLAT APPLICATION REVISED
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Revise initial application submission 60 days
30 days*
30 days**
117 days
66 days*
70 days**
Applicant
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
(1) Based upon Step #6, the applicant shall revise the application in conformance with the
first review cycle summary letter and the decisions rendered at the post summary letter
conference.
(a) All review comments must either be addressed, resolved in the post summary letter
conference, or waived before the application can be accepted for second cycle review. This must
be detailed in a written itemized report submitted as part of the application.
(b) All plan revisions must be highlighted in green.
(2) If major revisions occur to the plans, the plan shall revert to first review cycle review time
frames (Step #5).
(3) If the applicant fails to resubmit appropriately revised plans within the prescribed time
frames, and a time extension has not been requested and approved, the application will be
administratively denied and the file closed. Any further review of the application will require a
new first review cycle submission, with applicable fees, and compliance with current regulations.
49
April 2000
STEP #2.1
(If Necessary)
FINAL PLAN AND PLAT RESUBMISSION
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Resubmit revised application; case
manager analysis
3 day
2 days*
2 days**
120 days
68 days
72 days**
Applicant; Development
Services
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
(1) The revised application will be resubmitted to Development Services no later than the
deadline cited in the summary letter (i.e., sixty [60] days from the issuance of the first cycle
summary letter).
(2) All review comments contained in the first review cycle summary letter must either be
addressed via an application revision, or waived by the approving authority (i.e., VDOT, Service
Authority, etc.) before the revised submission can be accepted for the second review cycle.
(3) Upon resubmission of the revised application, it will be forwarded to the case manager for
analysis to determine the validity of the revisions. If the application is found to be acceptable and
to have satisfactorily addressed all issues in the first review cycle summary letter, it will be
immediately recommended for signature review.
(a) If the application is recommended for signature review by the case manager, the
applicant will be notified, and the submission will undergo a cursory review by the project review
team and a signature summary letter will be issued.
or (b) If the application is not recommended for signature review, the submission will be
distributed to the nonapproving first review cycle agencies for the second review cycle.
Additional agencies may be included in the review, even though they approved the application
during the first review cycle, if revisions to the plans have resulted in significant alterations of
those agencies' concerns.
50
April 2000
STEP #4.1
(If Necessary)
PLAN AND PLAT DISTRIBUTION
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Development Services distributes
plan to nonapproving review
agencies
1 day
1 day*
1 day**
121 days
69 days*
73 days**
Development Services
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
The application is distributed to the review agencies that did not approve the first cycle plan
(Department of Public Works, Service Authority, VDOT, Health Department, Virginia Health
Department, Park Authority, School Administration, Dale Service Corporation, Virginia
American Water Company, Fire and Rescue, and the OIT/Information Resources Management
Division).
51
April 2000
STEP #5.1
(If Necessary)
FINAL PLAN AND PLAT REVIEW AND COMMENT
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Review agency analysis is undertaken
and results delivered to Development
Services
14 days
6 days*
9 days**
135 days
75 days*
82 days**
Development Services
case manager; Public
Works; VDOT;
OIT/Information
Resources Management
Division; Health
Department; Service
Authority; Fire and
Rescue; School
Administration; Park
Authority; Virginia
American Water Co.; and
Virginia Health
Department (as
appropriate)
Consolidation of engineering
comments by Public Works
3 days
3 days*
3 days**
138 days
78 days*
85 days**
Public Works
Summary letter issued 5 days
4 days*
4 days**
143 days
82 days*
89 days**
Development Services
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
(1) The revised application will be reviewed by the nonapproving first review cycle agencies
similarly as outlined in Step #5. Following the receipt of the consolidated engineering review
letter from the Department of Public Works, the Development Services project review team
chairman will author and issue a consolidated second review cycle summary letter.
(2) The internally consistent summary letter will be issued by the Development Services case
manager, within four (4) days of receipt of the Department of Public Works consolidated review
letter.
52
April 2000
STEP #6.1
(If Necessary)
FINAL PLAN AND PLAT POST SUMMARY LETTER CONFERENCE
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Hold conference; discuss findings
with applicant
20 days
15 days*
15 days**
163 days
97 days*
104 days**
Development Services
(appropriate project
review team chairman);
Public Works;
OIT/Information
Resources Management
Division; VDOT; Service
Authority; Health
Department; School
Administration; Park
Authority; Fire and Rescue
as appropriate; applicant
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
A post summary letter conference meeting, similar to the one outlined in Step #6, is held to
discuss all relevant aspects of the project in an attempt to resolve all issues.
53
April 2000
STEP #7.1
(If Necessary)
FINAL PLAN AND PLAT REVISED
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Revise initial application
submission
60 days
30 days*
30 days**
223 days
127 days*
134 days**
Applicant
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
Based upon Step #6.1, the applicant shall revise the application in conformance with the summary
letter and the decisions rendered at the post summary letter conference.
54
April 2000
STEP #2.2
(If Necessary)
FINAL PLAN AND PLAT RESUBMISSION
Third Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Resubmit revised application; case
manager analysis
3 days
3 days*
3 days**
226 days
130 days*
137 days**
Applicant; Development
Services
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
(1) The revised application will be resubmitted to Development Services no later than the
deadline cited in the summary letter (i.e., 60 days from the issuance of the second review cycle
summary letter).
(2) All review comments contained in the second cycle summary letter must either be
addressed via an application revision, or waived by the approving authority (i.e., VDOT, Service
Authority, etc.) before the revised submission can be accepted for third review cycle.
(3) Upon resubmission of the revised application, it shall be forwarded to the case manager
for analysis to determine the validity of the revisions. If the application is found to be acceptable
and to have satisfactorily addressed all issues in the second review cycle summary letter, it shall be
immediately recommended for signature review.
(a) If the application is recommended for signature review by the case manager, the
applicant shall be notified, and the submission shall undergo a cursory review by the project
review team and a signature summary letter shall be used.
or (b) If the application is not recommended for signature review, the submission will be
distributed to the nonapproving second review cycle agencies for the third review cycle.
Additional agencies may be included in the review, even though they approved the application
during the first and second review cycles, if revisions to the plans have resulted in significant
alterations of those agencies' concerns.
55
April 2000
STEP #4.2
(If Necessary)
FINAL PLAN AND PLAT DISTRIBUTION
Third Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Development Services distributes
plan to nonapproving review
agencies
1 day
1 day*
1 day**
227 days
131 days*
138 days**
Development Services
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
The application is distributed to the review agencies that did not approve the second cycle plan
(Department of Public Works, Service Authority, VDOT, Health Department, Virginia Health
Department, Park Authority, School Administration, Dale Service Corporation, Virginia
American Water Company, Fire and Rescue, and the OIT/Information Resources Management
Division) as appropriate.
56
April 2000
STEP #5.2
(If Necessary)
FINAL PLAN AND PLAT REVIEW AND COMMENT
Third Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Review agency analysis is
undertaken and results delivered
to Development Services
6 days
5 days*
6 days**
233 days
136 days*
144 days**
Development Services
case manager; Public
Works; VDOT;
OIT/Information
Resources Management
Division; Health
Department; Service
Authority; Fire and
Rescue; School
Administration; Park
Authority; Virginia
American Water Co.; Dale
Service Corp.; and
Virginia Health
Department (as
appropriate)
Consolidation of engineering
comments by Public Works
2 days
2 days*
2 days**
235 days
138 days*
146 days**
Public Works
Summary letter issued 4 days
3 days*
3 days**
239 days
141 days*
149 days**
Development Services
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
(1) The revised application will be reviewed by the nonapproving second review cycle
agencies similarly as outlined in Step #5.
(2) Following the receipt of the consolidated engineering review letter from the Department
of Public Works, the Development Services project review team chairman will author and issue a
consolidated third review cycle summary letter, within four (4) days of receipt of the
Development Services consolidated review letter.
57
April 2000
STEP #6.2
(If Necessary)
FINAL PLAN AND PLAT POST SUMMARY LETTER CONFERENCE
Third Review Cycle
Maximum Total
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Hold conference; discuss findings
with applicant
10 days
10 days*
15 days**
249 days
151 days*
164 days**
Development Services
(appropriate project review
team chairman);
OIT/Information Resources
Management Division;
VDOT; Service Authority;
Health Department; School
Administration; Park
Authority; Fire and Rescue
as appropriate; applicant
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
(1) A post summary letter conference meeting, similar to the one outlined in Step #6, is held
to discuss all relevant aspects of the project and attempt to resolve all issues.
(2) If all outstanding issues are not resolved, the application will be forwarded to the project
resolution committee by the case manager to resolve the remaining issues. The project review
committee is a management level committee composed of the chief of Development Services and
the chiefs of the Department of Public Works Transportation and Watershed Management
divisions. They shall hold a meeting with the applicant and the project review team to discuss the
remaining issues and determine a final recommendation to either approve or deny the application.
The project review committee shall schedule its meeting to discuss the project within
fourteen (14) business days of the date of the third review cycle post summary letter conference.
(3) If all issues are resolved by the project review committee, the application is returned to
the project review team chairman in order to issue a signature summary letter.
or 58
April 2000
If unresolved issues still remain, the project review team shall recommend to the director of
Planning to deny the application and administratively close the file. No additional action shall be
taken on the application without a new application submittal.
STEP #8
FINAL PLAN AND PLAT CURSORY SIGNATURE SUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Revise application and submit for
cursory signature review
30 days
25 days*
25 days**
279 days
176 days*
189 days**
Applicant
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
(1) Based upon either Step #6, Step #6.1, or Step #6.2, the applicant shall revise the
application in conformance with the signature summary letter. Five (5) copies of the revised
application shall be submitted to Development Services no later than the deadline cited in the
signature summary letter.
(2) All necessary easement and dedication deeds shall be executed and submitted for review
no later than this stage of the process, although they may be submitted for review at any earlier
stage of the process.
59
April 2000
STEP #9
FINAL PLAN AND PLAT CURSORY SIGNATURE REVIEW
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Conduct cursory review; write and
issue cursory review letter
5 days
3 days*
3 days**
284 days
179 days*
192 days**
Development Services;
Public Works; Service
Authority;
OIT/Information
Resources Management
Division
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
(1) The application shall undergo a cursory review by the project review team,
OIT/Information Resources Management Division and the Service Authority. A cursory review
letter is issued by the case manager citing any minor revisions necessary to be made to the
application prior to the plans being signed.
(2) All submitted deeds shall be forwarded to the county attorney for review and approval at
this time. Their review will utilize independent time frames.
60
April 2000
STEP #10
FINAL PLAN AND PLAT SIGNATURE SUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Revise application; submit for
approval
30 days
15 days*
15 days**
314 days
194 days*
207 days**
Applicant
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
(1) The application is revised based upon the cursory review letter and submitted for approval
and signature to Development Services.
(2) The submittal shall consist of:
(a) The specific number of plans and plats cited in the cursory review letter.
(b) Signed site development fee calculation sheet.
(c) Storm water management computations (if applicable).
(d) Storm water management maintenance agreement (if applicable).
(e) Executed deeds.
61
April 2000
STEP #11
FINAL PLAN AND PLAT APPROVAL AND SIGNATURE
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Sign application; issue plan
approval letter
5 days
5 days*
5 days**
319 days
199 days*
212 days**
Development Services
case manager (as
appropriate); Development
Services division chief
*These time frames note the priority processing times for the various steps.
**These time frames note the expedited processing times for applications submitted by designated
plans examiners for the various steps.
NOTES:
(1) Upon submittal, the application shall be checked by the Development Services case
manager for completeness as outlined in the signature summary letter. If the application is
complete, a plan approval letter shall be issued and the Development Services division chief shall
sign the plans, on behalf of the director of Planning.
(2) All final plan approvals are valid for five (5) years from the date of signature.
62
April 2000
4.04.5. Review and Approval Process for Simple Subdivisions, Resubdivisions,
Consolidations and Family Land Transfers.
STEP #1
PRESUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Applicant submits plan to the
OIT/Information Resources
Management Division; application
name approval, GPIN
identification, project number
N/A N/A Applicant;
OIT/Information
Resources Management
Division
NOTES:
All first-time application submissions must be processed by the OIT/Information Resources
Management Division prior to submittal to Development Services. The purpose is to identify the
existing parcel GPIN(s) associated with the application, assign a project number, and approve the
project name.
63
April 2000
STEP #2
APPLICATION SUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Applicant submits plan to
Development Services
1 day 1 day Applicant; Development
Services
NOTES:
(1) The applicant shall submit a complete application package, the requirements of which
vary, depending on the type of submission, and are available at the Development Services counter
which, at a minimum, shall include site plan, easement and/or subdivision plat as appropriate,
quality control checklist, development control form, fee calculation sheet, and fee check. Failure
to do so will result in their rejection for acceptance and, subsequently, delays.
(2) If applicable, any necessary or desired waiver requests should have previously been
submitted and acted upon prior to the application submittal.
(3) All County process times (days) shown are business days. All other times under the
control of the applicant are calendar days.
64
April 2000
STEP #3
QUALITY CONTROL REVIEW
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Quality control review; create file;
assign case manager
3 days 4 days Development Services
NOTES:
(1) The submission is checked for completeness based upon the minimum submission
requirements cited on the appropriate quality control checklist. County staff will also review the
applicant's fee calculation for accuracy. If the submitted fee is less than the approved fee by
twenty percent (20%) or more, the application is rejected. As a result of this quality control
review, the submission is either accepted for processing or rejected. If accepted, a file is
established and the applicant is so notified and told to submit the appropriate number of plans.
Review agencies are selected, as appropriate, depending on the type of application.
(2) If the application is rejected, it is returned to the applicant, along with a list of
deficiencies.
(3) A case manager is assigned to coordinate the review and processing of the application.
(4) All plans shall be designed in conformance with the current standards and regulations in
effect at the time of their first cycle submission.
65
April 2000
STEP #4
APPLICATION DISTRIBUTION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Development Services distributes
application to review agencies;
application data entered into LIS
1 day 5 days Development Services
NOTES:
The application is distributed to the appropriate review agencies selected during the quality
control review. All the necessary application submission data is entered into LIS.
66
April 2000
STEP #5
APPLICATION REVIEW AND COMMENT
First Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Review agency analysis is
undertaken and results delivered
to Development Services
12 days 17 days Development Services
and, as appropriate,
OIT/Information
Resources Management
Division; Health
Department; County
Attorney
Consolidation of comments and
summary letter issued
5 days 22 days Development Services
case manager
NOTES:
(1) The case manager is the focal point of the overall review process. As such, he/she should
be apprised of all meetings between the applicant and review agencies to discuss major issues.
While the case manager may choose not to participate in a specific meeting, he/she should be
afforded the opportunity.
(2) The application analysis by the various review agencies is meant to conduct a technical
and administrative review for compliance with the Zoning Ordinance, DCSM, and any related
regulations administered by the various agencies.
(3) All review comments prepared by the various review agencies for these simple type
applications shall be forwarded to the Office of Planning case manager.
(4) The case manager will issue the first review cycle summary letter within four (4) days of
the receipt of all the agencies' review letters. It will outline the plan deficiencies that must be
addressed and any additional comments, concerns, and issues raised by the various review
agencies.
(a) The date and time of the post summary letter conference will be cited in the summary
letter, and
(b) The application resubmission date and the required number of plans and/or plats to
be resubmitted will also be cited.
67
April 2000
STEP #6
POST SUMMARY LETTER CONFERENCE
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Hold conference; discuss findings
with applicant
15 days 37 days Development Services and
review agencies, as
appropriate; applicant
NOTES:
(1) The meeting is held to discuss all relevant aspects of the application and attempt to
resolve all issues identified in the summary letter. The meeting is scheduled, coordinated and
chaired by the Development Services case manager.
Prior to the meeting, the applicant shall attempt to resolve all issues possible. Any
subsequent approvals by agencies shall be documented prior to or at the meeting. All issues will
be considered unresolved until documented.
(2) The applicant shall submit a response letter, addressing all comments contained in the
summary letter, to the case manager three (3) days prior to the post summary letter conference
date.
(3) If all the comments raised in the summary letter are adequately addressed during the
meeting, the case manager may immediately recommend the application for signature. A
signature summary letter will be issued within four (4) days of the meeting.
(4) If all comments are not adequately addressed, the applicant will be instructed to make
revisions to the plan and resubmit them for a second review cycle.
68
April 2000
STEP #7
APPLICATION REVISED
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Revise initial application
submission
45 days 82 days Applicant
NOTES:
(1) Based upon Step #6, the applicant will revise the application in conformance with the first
review cycle summary letter and the decisions rendered at the post summary letter conference.
(a) All review comments must either be addressed, resolved in the post summary letter
conference, or waived before the application can be accepted for the second review cycle. This
must be detailed in a written itemized report submitted as part of the application.
(b) All plan revisions must be highlighted in green.
(2) If the applicant fails to resubmit an appropriately revised application within the prescribed
time frames, and a time extension has not been requested and approved, the application will be
administratively denied and the file closed. Any further review of the application will require a
new first review cycle submission, with applicable fees, and compliance with current regulations.
69
April 2000
STEP #2.1
(If Necessary)
APPLICATION SUBMISSION
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Submit revised application; case
manager analysis
3 days 85 days Applicant; Development
Services
NOTES:
(1) The revised application shall be resubmitted to Development Services no later than the
deadline cited in the first review cycle summary letter.
(2) All review comments contained in the first review cycle summary letter must either be
addressed via a revision or waived by the approving authority (i.e., VDOT, Service Authority,
etc.) before the revised submission can be accepted for the second review cycle.
(3) Upon resubmission of revised application, it shall be forwarded to the case manager for
analysis to determine the validity of the revisions. If the application is found to be acceptable and
to have satisfactorily addressed all issues in the first cycle summary letter, it shall be immediately
recommended for signature review.
(a) If the application is recommended for signature review by the case manager, the
applicant shall be notified and the application shall undergo a cursory review and a signature
summary letter shall be issued.
or (b) If the application is not recommended for signature review, it shall be distributed to
the nonapproving first review cycle agencies for second review cycle.
70
April 2000
STEP #4.1
(If Necessary)
APPLICATION DISTRIBUTION
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Development Services distributes
application to nonapproving
review agencies
1 day 86 days Development Services
NOTES:
The application is distributed to the review agencies that did not approve the first review cycle
submission.
71
April 2000
STEP #5.1
(If Necessary)
APPLICATION REVIEW AND COMMENT
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Review agency analysis is
undertaken and results delivered
to Development Services
8 days 94 days Development Services and
Review Agencies, as
appropriate
Summary letter issued 5 days 99 days Development Services
case manager
NOTES:
(1) The revised application shall be reviewed by the nonapproving first cycle review agencies
in similar fashion as outlined in Step #5.
(2) The case manager shall issue the second review cycle summary letter within four (4) days
of the receipt of all the agencies' review letters.
(a) If necessary, the date and time of the post summary letter conference will be cited in
the summary letter.
(b) If all review agencies recommend approval, the case manager shall issue a signature
summary letter.
72
April 2000
STEP #6.1
(If Necessary)
POST SUMMARY LETTER CONFERENCE
Second Review Cycle
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Hold conference; discuss findings
with applicant
10 days 109 days Development Services and
review agencies, as
appropriate; applicant
NOTES:
(1) The second review cycle post summary letter conference, similar to the one outlined in
Step #6, is held to discuss all relevant aspects of the revised application and resolve all issues.
(2) No more than two (2) review cycles will be allowed for these types of applications.
(3) If all issues are resolved, the case manager shall recommend the application for signature
review and shall issue a signature summary letter.
or (4) If all issues are not resolved, the application shall be forwarded to the project resolution
committee to resolve the remaining issues and determine a final recommendation to either
approve or deny the application.
The project review committee shall schedule its meeting within fourteen (14) days of the
date of the second review cycle post summary letter conference.
73
April 2000
STEP #7
CURSORY SIGNATURE SUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Revise application and submit for
cursory signature review
30 days 139 days Applicant
NOTES:
(1) Based on either Step #6 or Step #6.1, the applicant shall revise the application in
accordance with the signature summary letter. The specified number of copies of the revised
application shall be submitted to Development Services no later than the date specified in the
summary letter.
(2) All necessary easement and dedication deeds shall be executed and submitted for review
no later than this stage of the process, although they may be submitted for review at any earlier
time.
74
April 2000
STEP #8
CURSORY SIGNATURE REVIEW
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Conduct cursory review; write and
issue cursory review letter
5 days 144 days Development Services;
Public Works; Service
Authority;
OIT/Information
Resources Management
Division (as appropriate)
NOTES:
(1) The application undergoes a cursory review by the case manager and other appropriate
review agencies as necessary. A cursory review letter is issued by the case manager citing any
minor revisions necessary to be made to the application prior to the plans being signed.
(2) All submitted deeds shall be forwarded to the county attorney for review and approval at
this time. Their review will utilize independent time frames.
STEP #9
SIGNATURE SUBMISSION
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Revise application; submit for
approval and signature
30 days 174 days Applicant
NOTES:
The application is revised based upon the cursory review letter and submitted for approval and
signature to Development Services.
75
April 2000
STEP #10
APPLICATION APPROVAL AND SIGNATURE
Subtasks
Maximum
Time for
Completion
Total
Elapsed
Time
Responsible
Party/Agency
Sign application 3 days 177 days Development Services
NOTES:
(1) Upon submittal, the application shall be checked for completeness by the case manager.
If complete, the application will be stamped and signed by the chief of Development Services and
a plan approval letter shall be issued.
(2) All final approvals are valid for five (5) years from the date of signature. Within the
period of validity, all plats and deeds associated with the application must be recorded.
76
April 2000
4.04.6. Review and Approval Process for Revisions to Approved Plans.
All applications for revisions to approved sketch, preliminary residential, and final plans and plats
shall be submitted to Development Services. Following their formal intake, the application shall
be routed to quality control for conformance with the appropriate required checklist(s), review fee
verification, and determination of the appropriate review time frames. These time frames will be
determined based on the complexity of the proposed revision.
A. If quality control determines the revision is major in nature, the following time frames will
be assigned:
(1) Sketch plans shall be processed as outlined in Section 4.04.1.
(2) Preliminary residential site plans shall be processed as outlined in Section 4.04.2,
except the review times shall be ten (10) days for the first review cycle and five (5) days for the
second review cycle.
(3) Preliminary residential subdivision plans shall be processed as outlined in Section
4.04.3, except the review times shall be ten (10) days for the first cycle and five (5) days for the
second cycle, and the need for a new Planning Commission approval will also be determined at
this time.
(4) Final site and subdivision plans and plats shall be processed as outlined in Section
4.04.4, except the review times shall be fifteen (15) days for the first cycle, ten (10) days for the
second cycle and seven (7) days for the third cycle.
B. If quality control determines the revision is minor in nature, they will establish a tailored,
abbreviated review process for the application, based on the plan type.
C. As part of the review process for revisions to final plans and plats, a cost estimate will be
established for any additional improvements shown on the plan. If a sufficient bond has
previously been posted with the Office of Planning, no additional bond shall be required. If
Development Services determines, based on the new bond estimate approved by the Department
of Public Works, that the previously posted bond is not sufficient to cover the cost of additional
improvements, an additional amount shall be posted in accordance with Section 4.07.
4.04.7. Minor Site Plan Process.
Minor site plans depict proposed improvements to a site/parcel for which there was either never a
previously approved site plan, or if there was an approved site plan, it has been closed. (See
Section 4.03.4 for additional details.)
A. A complete submission shall be made to the Office of Planning Development Services
Division and shall include a development control form, minor site plan checklist, fee calculation
sheet, review fee, and waiver request(s), if applicable. Minor site plans that include required plats
shall be sealed by a design professional.
77
April 2000
B. Processing. Prior to the formal submission of a minor site plan application, a
presubmission meeting shall be requested and held. The applicant is responsible for arranging the
meeting with either the chief or assistant chief of Development Services. This meeting shall
establish if the proposed improvements meet the guidelines cited in Section 4.03.4 above.
(1) If the application is found acceptable, it will be distributed for review to a
Development Services case manager, and the Department of Public Works, Fire Marshal,
OIT/Information Resources Management Division, Service Authority, and Health Department, as
necessary.
(2) A maximum of two (2) review cycles shall be allowed for each application. The first
cycle shall be fourteen (14) days and, if necessary, the second cycle shall be ten (10) days. At the
end of each review cycle, a summary letter shall be issued citing all necessary application
revisions. When a resubmission is required, it must be made within two (2) weeks of the issuance
of the summary letter.
C. Approval of Validity. All minor site plan approvals shall be valid for one (1) year from
their date of approval. Within that period of validity, the following items must be completed:
(1) Record all plats and deeds (if applicable).
(2) Post an erosion control escrow (if applicable).
(3) Complete any additional special items, agreements and post any other escrows
enumerated in the plan approval letter.
(4) Obtain a site development permit (if applicable).
Failure to complete all the items enumerated above during the approval validity period
shall cause the approval to expire and void the plan.
4.04.8. Administrative Plan Process.
Administrative reviews are reviews by the Office of Planning of minor revisions to previously
approved plan or minor development (as cited in Section 4.03.5) that do not necessitate the
formal submission of complete site plans, as determined by the chief or assistant chief of the
Division of Development Services. Where necessary, a cursory review by other review agencies
may be requested by staff.
A. A complete submission shall include one copy of a plan, which may be a nonengineered
sketch, and a written request for the administrative review. If the proposed improvement is a
revision to a previously approved plan, then the plan will require a seal of a licensed design
professional.
B. Processing. The review shall occur within the Office of Planning. The assigned case
manager may choose to consult with additional agencies in certain instances.
78
April 2000
Within two (2) weeks of submittal, a summary letter shall be issued. It will provide the
applicant with the results of the review (approval, rejection or revision). Upon approval of the
request, the summary letter shall request the necessary review fee and specify the number of plans
to be submitted for signature.
C. Validity. All administrative review approvals shall be valid for one (1) year from their
date of approval. Within that period of validity, the following items must be completed:
(1) Record all plats and deeds (if applicable).
(2) Post an erosion control escrow (if applicable).
(3) Complete any additional special items, agreements and post any other escrows
enumerated in the plan approval letter.
(4) Obtain a site development permit or zoning certificate (if applicable).
Failure to complete all the items enumerated above during the approval validity period
shall cause the approval to expire and void the plan.
4.04.9. Time Extensions for Application Resubmissions.
The director of Planning, or the designee may, upon written request, accompanied by the
appropriate fee, extend the resubmission date of an application. No such extension may exceed an
additional sixty (60) day time period for final plans and forty-five (45) days for preliminary
residential plans.
The following guidelines shall be utilized to govern the approval of such requests. Their use is
meant to assure that applications proceed through the review and approval process as
expeditiously as possible to assure that unnecessary delays are not created by either the public or
private sector, and that similar project requests are acted upon in a similar manner. In each
instance, the reasons enumerated below shall be considered the only valid reasons for approval of
resubmission time extensions.
A. No more than four (4) standard extension requests shall be granted during the complete
review and approval process (first cycle submission thru signature) of an application. The
following shall be considered valid reasons for approval of the extensions:
(1) Problems/difficulties with off-site easement/right-of-way acquisition.
(2) Vacation/abandonment/condemnation of easements or right-of-way.
(3) Approval required from a state and/or federal agency prior to County approval.
(4) The inability of an applicant to obtain a decision (not a submission review) from a
state agency (State Health Department, State Water Control Board, VDOT, etc.) which is
necessary for plan approval/project construction.
79
April 2000
(5) Revisions in state/federal regulations which are effective immediately and of which
the applicant was not aware.
(6) The necessity to conduct a study, integral to the plan approval, such as for soils,
wetlands, traffic, etc., which becomes evident while the plans are under review.
(7) Plan revisions necessitated by review comments.
(8) Bank/lending institution renegotiation of project financing, which requires major plan
revisions to be made (evidence of same must be provided).
(9) Other specific reasons as deemed valid by the director of Planning.
B. Additional extension requests may be granted by the director of Planning upon approval
of a waiver. For such requests, only the following reasons shall be considered valid for their
approval:
(1) Problems/difficulties with off-site easement/right-of-way acquisition.
(2) Vacation/abandonment/condemnation of easements or rights-of-way.
(3) Approval required from a state and/or federal agency prior to County approval.
4.04.10. Final Site Development Plan Validity.
All final site and subdivision plans and plats shall be valid for five (5) years from their date of
approval.
A. Requirements to be Completed Immediately Following Receipt of Final Approval. The
applicant shall complete the items listed below, subsequent to the receipt of final approval:
(1) For site plans, record all related plats immediately following final approval (within
thirty [30] days) without posting a performance bond and agreement.
(2) For subdivisions, record all related off-site plats immediately following approval
(within thirty [30] days) without posting a performance bond and agreement. All remaining
related plats (on-site plats) shall not be recorded until a performance bond and agreement has
been posted.
(3) Site preparation permits may be issued subsequent to recording the appropriate plats
prior to the posting of a performance bond and agreement, once the following items have been
completed:
(a) Payment of any monetary and/or proffered contributions and/or obligations
referenced in the plan approval letter.
80
April 2000
(b) Post a conservation escrow and agreement in an amount sufficient to defray the
cost of restoring the project site to a safe condition, if the developer fails to diligently pursue
construction of the permitted improvements in the period of time specified in the agreement. This
escrow shall include costs for items such as erosion and sediment control, grading of dangerous
slopes, reforestation, seeding and stabilizing denuded areas, completing and/or covering partially
completed structures, etc. This escrow will be released upon the posting of an erosion control
escrow and performance bond and agreement.
(c) The amount of the conservation escrow shall be equal to ten (10) percent of the
project's approved unit price list amount (approved bond amount less the inflation factor and the
administrative costs). The conservation escrow shall be a cash escrow or letter of credit in
accordance with Section 4.07.2.C. of this manual.
(d) Signing of a comprehensive inspection agreement, by either the developer or
contractor, if the project includes streets to be dedicated for public use and maintenance.
(e) Complete any additional special items, agreements, and/or post any additional
escrows enumerated in the plan approval letter.
(4) A performance bond and agreement shall be posted, in an amount sufficient to defray
the cost of installation for any uncompleted remaining improvements, as enumerated in Section
4.07 within twelve (12) months of the issuance of site preparation permits. Once this occurs, the
site preparation permit shall be replaced, at no additional cost, by the issuance of a site
development permit.
B. Requirements to be Completed During the Final Plan Validity Period: During the final
plan validity period, the applicant shall complete the following items or cause the approval to
expire:
(1) Post a construction performance bond and agreement in accordance with Section
130.00 of the DCSM, if applicable. This is a prerequisite to the release of certain plats and deeds
for recordation, issuance of site development permits for uses that are neither targeted industries
nor basic businesses, building permits, occupancy permits, etc.
(2) Payment of any monetary and/or proffered contributions and/or obligations, as
established during the plan approval process, and referenced in the plan approval letter. This is a
prerequisite to the release of the plats for recordation, or the issuance of site preparation permits,
site development permits, building permits, and/or occupancy permits.
(3) Recordation of all plats, along with their associated deeds. Following recordation of
each plat and deed, a copy of the recording receipt, a reproducible mylar copy of the plat, and a
copy of the accompanying deed will be returned to the Office of Planning. Recordation of all
plats related to site plans and off-site plats related to subdivisions, is a prerequisite to the issuance
of site preparations permits. Recordation of all plats for site plans and subdivisions is a
prerequisite to the issuance of site development permits, building permits, and/or occupancy
permits.
81
April 2000
For subdivisions, all recording information (deed book and page number citations)
shall be shown on all approved, but unsigned, internal project phase plats.
(4) Post an erosion control escrow in accordance with Section 760.00 of the DCSM.
This is a prerequisite to the issuance of either site preparation permits or site development
permits.
(5) Signing of a comprehensive inspection agreement by the developer, if the project
includes any streets to be dedicated for public use and maintenance. This is a prerequisite to the
issuance of either site preparation permits or site development permits.
(6) Post a landscaping escrow in accordance with Section 800.00 of the DCSM, if
applicable. This is a prerequisite to the issuance of occupancy permits.
(7) Complete any other special items, agreements and/or post any other escrows
enumerated in the plan approval letter. This is a prerequisite to the issuance of site development
permits, building permits, and/or occupancy permits.
(8) Obtain a site development permit, the fee for which is enumerated in the plan
approval letter. This is a prerequisite to the issuance of building permits.
C. Following the completion of the above-enumerated items, the Office of Planning will
issue a building permit release letter. This letter will indicate that all regulatory requirements have
been satisfied and will recommend the issuance of building permits. The letter will also enumerate
any additional specific items and/or requirements that must be completed prior to the issuance of
building or occupancy permits, if applicable.
D. Failure to complete all items enumerated in Section 4.04.10(B) above during the final
plan validity period shall cause the approval to expire and void the final site development plans. If
the final approval is voided, further consideration of the final site development plans will require a
new application submission, payment of applicable fees, and compliance with all regulations in
effect at the time of application acceptance.
E. Once the performance agreement and bond have been posted, in accordance with Section
4.07, the plan approval shall remain valid and be coincident with the expiration of the performance
agreement. The plan approval shall only be extended if, when, and for the length of time the
performance agreement is extended.
4.05. Minimum Plan and Plat Submission Requirements.
4.05.1. General Requirements.
A. Fees. The application and review fees for subdivision plans and plats and site plans are
established by resolution of the BOCS. As such, no fees can be waived by the director of
Planning. All application submissions shall be accompanied by the applicable fees. A complete
and certified Prince William County review fee calculation sheet shall be submitted as part of each
site development plan submission.
82
April 2000
(1) Partial payment of review fees may be acceptable to the director of Planning, or the
designee, under certain circumstances. Such fees may be accepted in two (2) installments, with
the first installment, which must equal at least fifty percent (50%) of the total fee, to be paid at the
time the application is submitted for review. The second installment shall be paid upon approval
of the application, or within one (1) year from the date of initial application submission, whichever
is earlier.
(2) In order to qualify for approval of a request for partial payments, the applicant shall
meet all the following criteria:
(a) The applicant shall not be delinquent in tax payments to the County, or has made
an arrangement for the payment of taxes satisfactory to the director of Finance.
(b) The project must add economic value to the County by providing either a
significant number of new jobs, a major planned transportation element which benefits the County
at large, a regional storm water management facility planned by the County, or substantially
increased real estate taxes.
(c) The project will provide affordable housing units recognized by the Department
of Housing and Community Development.
(d) A properly rated (see Section 4.07) financial institution has committed in writing
to finance the construction of the project.
(e) Review fees must total at least twenty-five thousand dollars ($25,000).
(f) The applicant enters into a binding agreement with the County for final payment.
B. Number of Plans to be Submitted:
(1) Sketch Plan Review, First Cycle Preliminary Residential and Final Plan Reviews.
The design professional shall initially submit one (1) complete set of plans. If the plan is accepted
through quality control, the applicant shall be so notified and told the number of plan sets to be
submitted. This number will be based on the number of review agencies that have been
established. Following the notification, the additional plan sets must be submitted within two (2)
business days, or the application will be rejected and returned by quality control to the applicant.
(a) All initial submissions shall be accompanied by all appropriate quality control
checklists, signed by the design professional who prepared the plans.
(b) The ultimate submission shall be accompanied by a certification that the
additional plan sets have not been revised since the initial submission, except for the enumerated
minor revisions requested by quality control.
(2) Second and Subsequent Cycle Preliminary Residential and Final Plan Reviews - The
applicant shall submit the number of plan sets cited in the previous review cycle summary letter.
83
April 2000
(3) Signature Submission. The applicant shall submit the number and type of plan sets
cited in the signature summary letter.
(4) Copyright notes will not be allowed on plans during any submission.
4.05.2. Sketch Plan Minimum Submission Requirements.
The following items shall be included with all sketch plan application submissions in order to have
them accepted for review:
A. Administrative Items:
A Prince William County development control form completed in its entirety. If the form
is not signed by the property owner, a power of attorney must accompany the form.
B. Plan Details:
(1) The sheet size shall not exceed 36" x 48" (900 millimeters x 1,219 millimeters).
Plans consisting of more than two (2) sheets shall be indexed and indicate match lines for lots of
five (5) acres (2.02 hectares) or less in size. The match lines shall follow property lines.
(2) A scale of no less than 1" = 200' (metric ratio 1:2000); this shall be displayed on all
plan sheets.
(3) Topographic contours with intervals no greater than five (5) feet (1.52 meters),
referred to USGS datum.
(4) Date of plan, north arrow, match lines, and sheet numbers.
(5) A vicinity map, preferably at a scale of 1" = 2000' (25 millimeters equals 609.76
meters), but no smaller than 1" = 3,000' (25 millimeters equals 914.64 meters).
(6) The present zoning of the project parcel(s), and all adjacent parcels, along with their
present use. The project name and Prince William County project number shall be noted for all
adjoining parcels, if applicable.
(7) The project(s) GPIN, and all adjacent parcels' GPINs.
(8) Total project site acreage.
(9) The proposed generalized pattern of lots and/or buildings (including the number and
size), street and/or travelway layout, off-street parking layout, recreation areas, open space, and
improvements to existing streets and rights-of-way, buffer, traffic counts (vehicles per day) and
storm water management facilities.
(10) All existing restrictions on the use of the land, including easements and covenants.
84
April 2000
(11) Existing drainage facilities, including major culverts, ponds, and streams.
(12) Location of all existing situations and buildings on the site.
(13) Note on plan stating the following: "This plan has not been reviewed for
conformance with rezoning proffers and/or special use permit conditions, if applicable. These will
be reviewed with the final plan submission."
4.05.3. Preliminary Residential Site and Subdivision Plan Minimum Submission
Requirements.
The following items shall be included with all preliminary residential plan application submissions,
in order to have them accepted for review:
A. Administrative Items:
(1) A Prince William County development control form completed in its entirety. If the
form is not signed by the property owner, a power of attorney must accompany the form.
(2) A separately bound and indexed booklet of project information which shall include.
(a) A copy of the stamped, approved proffer statement and analysis, if applicable.
(b) A copy of the stamped, approved special use permit conditions and analysis, if
applicable.
(c) A concurrent processing form, if the application is the subject of a rezoning,
proffer amendment and/or special use permit application at the time of submittal.
(d) A copy of either the Planning Commission resolution, or the director of
Planning's determination of conformity, if the application required a 456 public facilities review.
(3) Standard Prince William County cover sheet with the current revision date.
B. Plan Details:
(1) The sheet size shall not exceed 36" x 48" (900 millimeters x 1,219 millimeters).
Plans consisting of more than two (2) sheets shall be indexed and indicate match lines for lots of
five (5) acres (2.02 hectares) or less in size. The match lines shall follow property lines.
(2) A scale of no less than 1" = 100' (metric ratio 1:1,000); this shall be displayed on all
plan sheets.
85
April 2000
(3) Topographic contours with intervals no greater than five (5) feet (1.52 meters),
referred to USGS datum, extending fifty (50) feet (15.24 meters) beyond the parcel's property
lines, or additional distance, as may be necessary, in order to show major features or conditions
that may affect the project.
(4) Date of plan, north arrow, and sheet numbers.
(5) A vicinity map, preferably at a scale of 1" = 2,000' (metric ratio 1:25,000), but no
smaller than 1" = 3,000' (metric ratio 1:50,000).
(6) The present zoning of the project parcel(s) and present zoning and use of all adjacent
parcels. The Prince William County project and plan names and numbers shall be noted for all
adjoining parcels, if applicable.
(7) The project parcel(s) GPIN and all adjacent parcels' GPINs or GSINs. Residue use
parent GPIN or GSIN.
(8) Total project site acreage (hectares).
(9) Street rights-of-way, including name, number, and widths.
(10) All existing easements, including type, width, and use restrictions, if any.
(11) Existing storm drainage structures on the project parcel(s) and within fifty (50) feet
(15.24 meters) of the property lines or additional distance, as may be necessary, in order to show
major features or conditions that may affect the project, including type of pipe, sizes, and
direction of flow.
(12) Storm water management and BMP facilities on the project parcel(s) and within fifty
(50) feet (15.24 meters) of the property lines or additional distance, as may be necessary, in order
to show major features or conditions that may affect the project.
(13) Streams, ponds, marshes, approximate boundaries of wetland areas, including
names, if applicable, on the project parcel(s), and within fifty (50) feet (15.24 meters) of the
property lines or additional distance, as may be necessary, in order to show major features or
conditions that may affect the project.
(14) Preliminary resource protection area (RPA) boundary, as identified by the
preservation area site assessment, in accordance with Section 712.03 of the DCSM, or a note
indicating there are no mapped RPAs on the site.
(15) Preliminary resource management area (RMA) boundary, as identified by the RMA
limits study, if applicable, in accordance with Section 740.00 of the DCSM.
(16) The approximate one hundred (100) year flood area boundary and the source of the
information.
86
April 2000
(17) Buffers, parks, and recreation areas and the acreage (hectares) of all permanent open
spaces.
(18) Municipal or other publicly owned land within fifty (50) feet (15.24 meters) of the
property lines or additional distance, as may be necessary, in order to show major features or
conditions that may affect the project, including the distance to the nearest school or site.
(19) Existing utility lines and structures, such as water, sewer, gas, electric, telephone,
wells, and drainfields on the project parcel(s), including size or capacity, and within fifty (50) feet
(15.24 meters) of the property lines, or additional distance, as may be necessary, in order to show
major features or conditions that may affect the project.
(20) Location of all cemeteries and other historic sites on the parcel, or a statement that
no such facilities are known to exist on the site.
(21) Density tabulation, provided by section and overall total number of proposed lots
and/or dwelling units, and lot/unit numbers.
(22) Streets, roads, travelways, improvements to existing streets and other rights-of-way,
including widths, street classification, and preliminary anticipated traffic counts (vehicles per day).
(23) Pedestrian systems and bike trails.
(24) Lot layout, if applicable.
(25) Off-street parking layout, if applicable, including typical size, number of spaces by
location, and a tabulation.
(26) Proposed buildings, including use, height and, for site plans only, distance to
property lines, building restriction lines (if applicable), and any existing buildings or structures on
the property and within fifty (50) feet (15.24 meters) of the property line, or additional distance,
as may be necessary, in order to show major features or conditions that may affect the project.
(27) Schematic storm drainage systems and water and sewer systems, or drainfield and
well locations.
(28) Parcels to be dedicated to public use, including size and purpose.
(29) Tree canopy and tree save areas, if appropriate, including approximate acreages
(hectares), average size and dominant species.
(30) Comprehensive landscape plan in accordance with Section 800 of the DCSM, if
applicable.
87
April 2000
4.05.4 Final Site and Subdivision Plan Minimum Submission Requirements.
The following items shall be included with all final site and subdivision plan application
submissions in order to have them accepted for review:
A. Administrative Items:
(1) A Prince William County development control form completed in its entirety. If the
form is not signed by the property owner, a power of attorney must accompany the form.
(2) A completed standard Prince William County cover sheet with the current revision
date.
(3) A separately bound, sealed and indexed booklet of project information which shall
include:
(a) A copy of the stamped, approved proffer statement and analysis, if applicable.
(b) A copy of the stamped, approved special use permit conditions and analysis, if
applicable.
(c) A concurrent processing form if the application is the subject of a waiver
request, rezoning, proffer amendment and/or special use permit application at the time of
submittal.
(d) A copy of either the Planning Commission, or the director of Planning's
determination of conformity, if the application required a 456 public facilities review.
(e) Copies of any approved variances, waivers or letters of agreement concerning
the application.
(f) Copy of the approved general development plan (GDP).
(g) A copy of the unit price list, if not shown on the plans.
(h) Traffic impact analysis (Appendix A), if applicable, in accordance with Section
600.00 of the DCSM.
(i) Triparty maintenance agreements for sidewalks and/or landscaping, if applicable.
B. Plan Details:
(1) The sheet size shall not exceed 24" x 36" (600 millimeters x 900 millimeters). Plans
consisting of more than two (2) sheets shall be indexed and indicate match lines for lots of five (5)
acres (2.02 hectares) or less in size. The match lines shall follow property lines.
88
April 2000
(2) A scale of no less than 1" = 50' (metric ratio 1:500) for subdivisions, and 1" = 30'
(metric ratio 1:250) for site plans; this shall be displayed on all plan sheets.
(3) Topographic contours with intervals no greater than two (2) feet (0.50 meters),
referred to USGS datum, extending fifty (50) feet (15.24 meters) beyond the parcel's property
lines or additional distance, as may be necessary, in order to show major features or conditions
that may affect the project.
(4) Date of plan, north arrow with designation, and sheet numbers annotated in
consonance with any required subdivision plats, or meridian of record, if subdivision plats are not
required.
(5) A vicinity map preferably at a scale of 1" = 2,000' (metric ratio 1:25,000), but no
smaller than 1" - 3,000' (metric ratio 1:50,000).
(6) The seal and signature of the design professional engineer or land surveyor shall be
on each plan sheet. Architects may sign and seal site plans.
(7) The present zoning of the project parcel(s), and all adjacent parcels, along with their
present use. The project name and Prince William County project number shall be noted for all
adjoining parcels, if applicable.
(8) The project parcel(s) GPIN, and all adjacent parcels' GPINs or GSIN.
(9) Total project site acreage.
(10) Prince William County project and plan names and numbers for the subject property
and adjacent properties.
(11) Revisions to an approved plan shall have a completed revision block on each sheet
identifying the revisions. All revisions shall be circled in red on the initial submission. The project
and plan number(s) for any previously approved plan shall also be referenced on the revision.
(12) Boundary of record with 1:10,000 closure ratio, including area tabulation.
(13) Street rights-of-way, including names, recordation deed book and page references,
or route numbers and widths.
(14) All existing and proposed easements, including type, width, deed book and page
reference, and use restrictions, if any. If any proposed improvements are located within the
easements of these utilities, documentation shall be provided from the appropriate companies
acknowledging permission to make the improvements, prior to final plan approval. For
ingress/egress easements, a note shall be provided certifying that the applicant has been granted
the right to use, and make improvements, within the easements. For subdivisions, deed book and
page references for existing internal project easements do not need to be shown for plan approval
(see Section 4.04.10(B)(3)(a) of this manual).
89
April 2000
(15) Streams, ponds, marshes, wetland areas on the project parcel(s), and within one
hundred (100) feet (30.48 meters) of the property lines, including names, if applicable.
(16) Final resource protection area (RPA) boundary, as identified by the preservation
area site assessment, in accordance with Section 742.03 of the DCSM, or a note indicating there
are no mapped RPAs on the site.
(17) Final resource management area (RMA) boundary, as identified by the RMA Limits
Study, if applicable, in accordance with Section 742.09 of the DCSM.
(18) The one hundred (100) year flood area boundary and the source of the information.
(19) Permanent open spaces, tabulation in acreage (hectares), buffers, parks, and
recreation areas, including ownership and size of the facility.
(20) Municipal or other publicly owned land within fifty (50) feet (15.24 meters) of the
property lines, or additional distance, as may be necessary, in order to show major features or
conditions that may affect the project, including the distance to the nearest school or school site.
(21) Utility lines and structures, such as water, sewer, gas, electric, telephone, wells, and
drainfields on the project parcel(s), including size and/or capacity, and within fifty (50) feet (15.24
meters) of the property lines, or additional distance, as may be necessary, in order to show major
features or conditions that may affect the project.
(22) Buildings and other structures on the project parcel(s) and within fifty (50) feet
(15.24 meters) of the property lines, or additional distance, as may be necessary, in order to show
major features or conditions that may affect the project.
(23) Traffic counts (vehicles per day).
(24) All entrances labeled to proper VDOT or Prince William County standards.
(25) Percent of grade noted at all commercial entrances.
(26) Location of all cemeteries and other historic sites on the parcel, or a statement that
no such facilities are known to exist on the site.
(27) Any project which has within its limits one or more geodetic control monuments
shall show those moments with the following note:
"The geodetic control monument(s), list all pertinent monuments, located on or in
proximity to the site will not be disturbed. The developer assumes the responsibility for
replacement of the monument(s) should it/they be disturbed during any development related to
this project."
90
April 2000
(28) A subdivision, easement, and/or dedication plat(s), if applicable, in accordance with
Section 4.05.5. Subdivision and easement plats shall be included with the first cycle review
submission.
(29) Floodplain study, if applicable.
(30) Lot layout, including lot numbers, area of each lot, and street dedication area. All
resultant areas of recorded parcels, less than ten (10) acres (4.05 hectares) in size, shall be shown
on the plans and indicated in the area tabulation. All resultant areas of recorded parcels, ten (10)
acres (4.05 hectares) or greater in size, are considered as residue and shall be indicated in the area
tabulation but not shown on the plans.
(31) Density tabulation (provided by section and overall), total number of proposed lots
and/or dwelling units.
(32) Streets, roads, travelways, and other rights-of-way, including deed book and page
number, street classification, widths, rates of roadway superelevation, when applicable, vertical
curves with the sight distance noted, vertical and horizontal sight distances verified at all
intersections, and improvements within the state right-of-way. Guardrail and paved ditches shall
be shown as required. Handicapped access curb ramps shall be provided at all street intersections
on urban design roadways.
(33) Off-street parking (including handicap) and loading layout, if applicable, including
typical size, number of spaces by location, and a tabulation by use type.
(34) Existing and proposed buildings and structures, including use, height, square footage
(square meters), distance to property lines and between buildings, and any applicable building
restriction lines (site plan only).
(35) Utility lines and structures, including sewer, water, gas, wells, and drainfields with
sizes, types of pipe, plan and profile views, location of fire hydrants, control valves, pump
stations, and anticipated flows and calculations (three [3] copies of fire flow calculations
submitted separately). Proposed drainfields shall include the following note, if applicable: "The
proposed drainfields shall provide a reserve drainfield area at least equal to that of the primary
sewage disposal site."
(36) Utility easements, including gas, electric, telephone and cable television, with the
width and type indicated.
(37) Storm drainage system, including all required computations on the project parcel and
within fifty (50) feet (15.24 meters) of the property line, or additional distance, as may be
necessary, in order to show major features or conditions that may affect the project, with sizes,
type of pipe, gradients, invert elevations, direction of flow, drainage divides and areas for each
structure.
91
April 2000
(38) Storm water management and BMP facilities, including ten (10) and one hundred
(100) year water surface elevations and all required computations, access and maintenance
easements, and a storm water management fact sheet (if SWM/BMP has been approved with a
previous section, note the PWC plan number).
(39) Final grading plan.
(40) Limits of clearing and grading, marked and clearly labeled.
(41) Erosion and sediment control devices, their design and locations.
(42) Location of street name signs, traffic control signs, street lights, stubouts, and their
easements, if applicable.
(43) Buffer areas, screening, landscaping and tree canopy requirements, in accordance
with Section 800.00 of the DCSM.
(44) Tree save areas indicating dominant species and average size, area tabulations for
substantiating area size compliance, and proposed new tree plantings and landscaping, in
accordance with Section 800.00 of the DCSM.
4.05.5. Subdivision and Easement Plat Minimum Submission Requirements.
The following items shall be included with all required plats, including those for simple
subdivisions, family land transfers, resubdivisions, consolidations, right-of-way dedications,
easements, abandonments, vacations, and revisions to approved plats, in order to be accepted for
review:
A. Administrative Items:
A Prince William County development control form completed in its entirety. If the form
is not signed by the property owner, a power of attorney shall accompany the form.
B. Plat Details:
(1) The sheet size shall not exceed 18" x 24" (450 millimeters x 600 millimeters), nor be
smaller than 8 1/2" x 11" (215 millimeters x 275 millimeters). All copies shall be reproduced on
black or blue line paper, and conform to the Virginia State Library Board standards for plats.
Plats consisting of two (2) or more sheets shall be indexed and indicate match lines. For lots of
five (5) acres (2.02 hectares) in size or less, any necessary match lines shall follow property lines.
(2) A graphic scale of not less than 1" = 100' (metric ratio 1:1,000), which shall be
displayed on all plat sheets. Also, all plats shall use only one uniform scale.
92
April 2000
(3) Each sheet shall contain a title block which shall include: subdivision name, or
owner's name, in accordance with the instruments of record, name and address of the engineering
or surveying firm that prepared the plats, magisterial district name, date of preparation,
description of plat's purpose, and the Prince William County project and plan numbers and names,
and geographic subdivision identification number, once assigned. (The project number is assigned
by OIT/Information Resources Management Division prior to submission.)
(4) All plats shall contain a north arrow annotated with, and be referenced to:
(a) VCS 1983 north, as represented by the Prince William County geodetic
monument network; for subdivisions or resubdivisions, they shall comply with Section 120.00 of
the DCSM; or
(b) True north for subdivisions or resubdivisions not subject to Section 120.00 of
the DCSM; or
(c) North of record may be used for minor resubdivisions, consolidations, off-site
easements and off-site right-of-way dedications.
(5) Plats referenced to VCS 1983 shall annotate two property corners on each sheet with
complete VCS 1983 coordinate pairs (in international feet/meters). Each plat so referenced shall
be annotated in accordance with Section 120.00 of the DCSM. Assumed coordinate values or
grid tics shall not be shown on any plat.
(6) A vicinity map, preferably at a scale of 1' = 2,000' (metric ratio 1:25,000).
(7) Seal and signature of the land surveyor or professional engineer that prepared the
plat shall be on each plat sheet. Seals are not required to be signed until approval submission,
provided the following note is added: "This plat is for review purposes only and not for
recordation."
(8) A surveyor's certificate containing the following elements:
(a) The name of the current owner and the recordation reference of the most recent
instrument in the chain of title.
(b) For subdivisions and consolidations, the recordation reference of the previous
plat of subdivision or resubdivision, whichever is the case.
(c) A statement that the boundary of this subdivision, or resubdivision, is based on a
current field survey (in this case, it is expected and understood that the seal and signature of the
land surveyor evidences that the boundary shown complies with the minimum field practices for
such surveys in an urban area, as set forth in the rules and regulations of the State Board of
Architects, Professional Engineers, Land Surveyors, and Landscape Architects), or that the
boundary shown is the result of compilation from deeds and/or plats of record and, if a closed
boundary is shown, that the errors of closure ratio is greater than or equal to 1:10,000.
93
April 2000
(d) The meridian which the bearings are referenced to, and the method of
establishment.
(e) A statement that the iron pipes will be set in accordance with the Subdivision
Ordinance and Section 120.00F of the DCSM. This is not required for easement plats.
(9) A notarized owner's consent and dedication in substantially the following form: This
language is meant to be comprehensive in nature and is provided in this form in an attempt to
address all the various types of plats submitted for review and approval. Therefore, the
submitting land surveyor should extract and use from the language only those items relative to the
particular plat being prepared.
This statement shall be signed and dated prior to signature approval by the person(s)
with authority to bind the owner of the property so platted (title and name shall be reproduced
under the signature space), and shall be duly acknowledged before an officer authorized to take
the acknowledgment of deeds. Final plats shall be recorded in the land records of Prince William
County and a copy of the recordation receipt with the deed book and page numbers shall be
returned to the Office of Planning for inclusion in the project records. The statement shall
generally read as follows:
"The platting of dedication of the land shown hereon, and as described in the
surveyor's certificate, is with the free consent and in accordance with the desire of
the undersigned owner, proprietors, and trustees, if any. The undersigned hereby
expressly consent(s) to the dedication of the Board of County Supervisors, in fee
simple absolute, of all areas shown on this plat for roads, streets, alleys, schools,
parks and such other public uses as may be identified by specific use of name or by
the general designation 'for public use,' and further consent(s) to the dedication of
any easement indicated on such plat for public rights or passage, storm drainage, or
expressly identified for the installation of sewer, water, or other utility lines, or for
access thereto, or for construction easements, temporary or permanent, ultimately
to be owned, operated, or maintained by any public authority."
(10) All resultant areas of recorded parcels, less than ten (10) acres (4.05 hectares) in
size, shall be platted and shown on the plats, and indicated in the area tabulation. All resultant
areas of recorded parcels, ten (10) acres (4.05 hectares) or greater in size, are considered as
residue and shall be indicated in the area tabulation, but need not be platted.
(11) Area tabulation indicating (where applicable) the total site area, number of new lots
and/or parcels, number of recorded lots and/or parcels, residue of each recorded parcel, resulting
from the subdivision, new right-of-way dedications, and vacated rights-of-way.
(12) Individual lots, each identified by a separate and sequential number, in accordance
with Section 603.24 of the DCSM.
(13) The existing and all adjoining parcel(s) GPIN(s) or GSIN.
94
April 2000
(14) Subdivision, parcel, and lot boundaries with bearings and distances and/or complete
curve data. Internal lots shall be geometrically related to the boundary of the subdivision, or
section thereof. Curve data shall be shown on the same sheet as the curve it describes.
(15) All existing structures shown on the plat or an exhibit attached to the plat for
resubdivisions, consolidations, and family subdivisions.
(16) All applicable notes.
(17) Street addresses (assigned during the review process as necessary), in accordance
with Section 603.24 of the DCSM.
(18) The one hundred (100) year flood area boundary, when applicable, including ties to
property lines and corners, with bearings and distances and/or curve data, and labeled flood
hazard area.
(19) The RPA boundary, when applicable, including ties to property lines and corners,
with bearings and distances and/or curve data, labeled as such.
(20) The RMA boundary, when applicable, including ties to property lines and corners,
with bearings and distances and/or curve data, labeled as such.
(21) Proposed and existing easements annotated with the following: type, purpose, and
width, bearings and distances and/or curve data for centerlines, or limits, with ties to property
lines and corners (new easements only), deed book and page references for existing easements
and appropriate maintenance notes for all proposed easements, such as sight distance, utility,
buffer, storm drainage, water, sanitary sewer, etc.
Deed book and page references for existing internal project easements do not need
to be shown for plat approval (see Section 4.04.10(B)(3) of this manual.
(22) Proposed and existing streets within and/or adjacent to the subdivision, and provided
with the following: name, designator, route number or deed book and page references, if not
state maintained (existing streets only), centerlines, bearings and distances and curve data for the
rights-of-way, and each new right-of-way dedication annotated with the area and the phrase,
Hereby dedicated for public street purposes.
(23) Vacated streets and parcels with the area vacated and those areas reverting to
appropriate adjacent parcel(s).
(24) Existing and proposed drainfield locations shown on the plat or an exhibit and the
following note, if applicable, added to the plat:
The proposed drainfield(s) shall provide a reserve drainfield area at least equal to
that of the primary sewage disposal site.
(25) Existing and proposed well locations shown on the plat or an exhibit.
95
April 2000
(26) Application for a family subdivision, including the deed by which the owner obtained
the property, deed transferring the property and proof of relationship.
(27) All existing easements with deed book and page number or a note stating: All
underlying easements may not be indicated on this plat.
(28) The following note shall be included on the plat for all site or subdivision plats that
include a landscape plan: The owner of fee title to any property on which plant material has been
established in accordance with an approved landscape/planting plan shall be responsible for the
maintenance, repair and replacement of the approved plant material as required by the ordinance.
If a plat is not required, the note required above shall be shown on the landscape or
grading plan.
(29) Every use requiring establishment of a bufferyard shall note the following restriction
regarding the use of such buffer on a plat or other instrument recorded among the land records:
Land designated as bufferyard shall be landscaped and may only be used for structures, uses, or
facilities in accordance with the requirements of the Zoning Ordinance and the Design and
Construction Standards Manual.
4.06 Regulations and Procedures Governing the Conveyance of Real Property and
Easements to Prince William County.
4.06.1 General Requirements. Whenever an applicant proposes, or is legally required, to
convey interests in real property to the County, the following requirement shall govern:
A. If any such conveyances are made subject to any easements, rights-of-way, or other
restrictions, a title report shall be provided to and approved by the County. Such report shall be
prepared at the applicant's expense by an attorney or title issuance company approved by the
County. Such title report shall identify the nature and extend of such easements, rights-of-way,
and other conveyances of title subject to any conditions, restrictions, and encumbrances which the
County determines adversely affect the use for which the interest in land is to be dedicated. No
such conveyance may be subject to any restrictive covenants applicable to other properties of the
applicant, or to the project within which the subject property may lie, unless express prior
agreement by the BOCS has been made to the contrary. The county attorney shall review such
title report when provided, and shall indicate to the grantor in writing the County's acceptance or
rejection of the restrictions and encumbrances in the chain of title.
96
April 2000
B. When the BOCS agrees to accept a dedication of property, in compliance with a
proffered condition of a rezoning, with an express limit on the use of the property, a reverter
clause in substantially the following form may be contained in the deed:
The property is hereby conveyed expressly for public use by agencies of Prince William
County, the Commonwealth of Virginia, or the United States of America. In the event
that the property is conveyed to other users for private purposes, it shall be lawful for
the dedicator, or his heirs or assigns, to reenter and repossess the property herein
dedicated, in accordance with the rules of common law of Virginia.
C. All deeds and title reports required hereby shall be submitted to the Office of Planning for
review no later than when the final plans and plats are submitted for signature approval. In
addition, a copy of every instrument mentioned in deed or title report as affecting the estate which
is to be conveyed to Prince William County shall also be submitted. They shall be forwarded to
the county attorney who shall note approval or disapproval, specifically noting reasons for
disapproval, if any, of any portion of the assembly.
4.07 Performance Bonds, Agreements and Guarantees.
The following regulations shall be utilized to govern the acceptance, processing and close-out of
all forms of guarantees, when required by Section 130.00 of the DCSM.
4.07.1 Performance Agreement. A performance agreement, supported by a form of guarantee,
shall be required on all projects. This agreement and guarantee shall obligate the applicant to
construct all the legally required improvements on approved projects in a timely manner and in
accordance with applicable standards. Public agencies of Prince William County seeking site
development plan approval may supply a letter of intent to comply with this requirement,
provided that a completion bond is secured from the contractor performing the construction,
guaranteeing the construction will be completed in accordance with the approved site
development plans and County requirements.
A. The initial agreement, which shall be between the applicant and the BOCS, may be for a
maximum period of eighteen (18) months. Thereafter, time extensions may be permitted in
accordance with Section 4.07.3 below.
B. The aggregate of all forms of surety posted on a project should not exceed the total of
the estimated cost of construction, based on the County's unit price list, with additional reasonable
allowances for administrative costs, inflation and potential damage to existing roads and utilities.
4.07.2 Corporate Surety Bonds. Corporate surety bonds, cash, letters of credit and set-aside
agreements are the only forms of guarantees acceptable to the County.
97
April 2000
A. Corporate surety bonds shall be furnished by an insurance company, licensed to transact
fidelity and surety insurance in Virginia, which will guarantee the full amount of the bond. The
surety shall be satisfactory to the County and have a best key rating of AXV or higher.
Alternatively, it may hold a certificate of authority as an acceptable surety for federal bonds. Such
bonds shall obligate the surety, when notified of the principal's default, to elect either to perform
in its principal's stead or to pay the face amount of the bond, or any lesser appropriate amount
determined by the director of Planning. Should the rating of the surety fall below Prince William
County's minimum acceptable rating, the applicant will be so notified, and shall provide an
acceptable substitute surety. This action shall be completed within sixty (60) days of notification,
or default proceedings shall be initiated.
B. Cash may also be furnished to the County as a project's bond. When this option is
utilized, the funds will be deposited in interest-bearing accounts by the director of Finance. In the
event of default by the developer, interest that accrues on such funds shall be available to Prince
William County for application to the cost of completing required improvements. In the event of
no default by the developer, such interest shall accrue for the benefit of the developer and shall be
returned upon release.
C. Letters of credit will be accepted as bonds, if they meet the following criteria:
(1) The issuing institution must meet the County's standards for providing satisfactory
performance guarantees.
(a) One aspect of this assessment shall be that issuers must possess a rating of 20(c)
or better in the latest edition of Sheshunoff's Quarterly Ratings for Banks and Savings and Loan
Associates (Sheshunoff's). This rating must also be met by issuers of standby letters of credit in
support of extension requests for agreements that have expired.
(b) The County may accept a letter of credit issued by a nonqualifying bank, when
such bank has issued to the County as beneficiary an additional letter of credit of equal value from
a qualifying bank.
(c) Letters of credit may be accepted from a foreign bank, provided they are issued
by a branch located in the United States, subject to a revision of the uniform commercial code,
and the bank's stability can be satisfactorily determined by the Office of Planning.
(2) The performance agreement must expire a minimum of six (6) months prior to
expiration of the letter of credit. The letter of credit must be irrevocable during that time period.
(3) A minimum ninety (90) day notification period of the lending institution's election not
to extend the validity of the letter of credit is required and must be sent by certified mail to the
director of Planning. Failure to give notice as required shall automatically extend the letter of
credit for successive additional six (6) month periods. (Such provision must be included in the
letter of credit.) Should the developer not provide a substitute letter of credit at least sixty (60)
days prior to the expiration, or complete all requirements to effect release, the funds shall be
drawn immediately thereafter, and a default action shall be initiated.
98
April 2000
D. A set-aside agreement is an agreement among the developer, a lending institution, which
is making the development or construction loan to the developer for the project, and Prince
William County. The agreement must commit the bond funds to payment of the required bonded
improvements and no other purposes.
(1) The director of Planning shall have twenty-one (21) days in which to approve or
disapprove any expenditure, upon written request, for approval identifying the project and
agreement and nature of proposed expenditure, and balance of the completion fund.
(2) The County shall not approve more than one (1) partial reduction per month, except
as authorized by the director of Planning. Each quarterly reduction request shall require an
inspection by the County prior to its approval. Any interim reduction requests shall be
accompanied by a certificate of inspection from a professional engineer or land surveyor. Said
certificate shall identify the work completed since the last request, an approved reduction amount
since the last request, and a statement that the work described has been performed in strict
conformity with the approved plans and meets all applicable standards.
No interim partial reduction request shall be approved for more than fifteen percent
(15%) of the remaining amount of the set-aside.
E. Forms: The director of Planning shall approve, and may amend from time to time, all
standard forms to be used for performance agreements and bonds. No deviations shall be
accepted, unless approved by the county attorney for conformity with this policy and all
applicable requirements.
F. Upon request, and following approval, any of the acceptable four (4) forms of guarantees
described above may be substituted for a correlative form.
4.07.3 Extensions and Rebonding of Agreements.
A. When a developer enters into an agreement with Prince William County, it is understood
that all the necessary physical improvements must be completed in the specified period of time. If
all the noted improvements are not completed within this time period, and no extension has been
obtained, or a replacement agreement and bond have not been submitted and approved with a new
expiration date, the agreement shall be deemed in default.
B. Approximately sixty (60) days prior to the expiration of the agreement, Prince William
County shall notify the developer in writing of the expiration date. The notification is meant to
caution the developer that he will be in default unless the work is either completed in accordance
with the agreement and approved plans, or an extension of time is obtained in accordance with the
requirements of the policy.
C. The developer shall make a written request to the director of Planning for an extension of
the performance agreement's expiration date.
99
April 2000
(1) The first request may be for a period not to exceed three (3) years. In order to
receive the maximum extension, the developer must demonstrate that the extension would be in
the best interest of Prince William County.
(2) If subsequent extensions are required, they will be for maximum periods of one (1)
year each. All requests shall be made fourteen (14) calendar days prior to the expiration date.
(3) The developer must indicate the reasons and conditions which have precluded him
from completing the required physical improvements. The developer must also present written
consent to the request from all sureties involved, including corporate surety companies. In
addition, the request shall contain a detailed cost estimate of the work remaining, together with a
projected timetable for completion. The current County unit price list data shall be utilized in
compiling this information.
(4) The director of Planning may grant extensions of less than one (1) year due to
conditions outlined in D. below.
(5) A fee to cover any necessary inspection and administrative costs shall be paid in
accordance with the fee schedule for such inspections.
D. If the developer has requested an extension or a substitute agreement and surety, the
Office of Planning will review the project particulars and the request submitted by the developer.
The factors considered by the Office of Planning shall include the following:
(1) Percentage of the project that has been completed. This shall be viewed as the
percentage (based on the unit price list [UPL] dollar value) of the bonded improvements
completed (adjusted for inflation). Generally, this should be at least fifty percent (50%) for the
first extension request and eighty-five percent (85%) for the second request.
(2) Number of homes/units completed, occupied, and served by public facilities, if
applicable. Generally, this should be at least ten percent (10%) of the project for each year (or
prorated portion thereof) the project has been under construction.
(3) Developer's performance history on prior projects in Prince William County. This
shall be based on the developer's previous number of defaults.
(4) The collective number, type, and validity of complaints lodged against the developer.
(5) If the project provides access and/or infrastructure necessary for other projects which
are either under construction or approved and no site development permits have been issued.
(6) If the project provides for the construction of connector/arterial roads, or regional
storm water management facilities.
100
April 2000
E. In the event the developer does not respond to the letter sent by Prince William County
cautioning him of impending default, and the project is not completed by the expiration date, the
matter shall be reviewed by the director of Planning for appropriate action, including referral to
the Board of County Supervisors for its actions.
F. Following the initial extension, if no substantial construction has been initiated, any
further extension shall be governed by the following criteria:
(1) For approved final plans which have been bonded, have recorded plats and that have
not initiated substantial construction and are not proceeding:
(a) For all such plans not qualifying for the five (5) year plan validity law, although
their approval will be valid as long as their performance bond and agreement are valid, the
director of Planning may extend the bond and agreement for a maximum of one (1) additional
year beyond the initial (present) period. Construction must have been initiated and be diligently
pursued within that additional year or the approval shall be automatically void.
(b) For all such plans that qualify for the five (5) year plan approval law, although
their approval will remain valid for five (5) years from their date of approval, even though their
performance bond and agreement may not be valid, the director of Planning may extend the bond
and agreement for a maximum of one (1) additional year, or the remaining plan validity time,
whichever is less.
(2) For approved final plans which have been bonded, have recorded plats, and although
construction has been initiated, it is proceeding slower than necessary:
(a) For all such plans not qualifying for the five (5) year plan validity law (although
their approval will be valid as long as their performance bond and agreement are valid), the
director of Planning may extend their bond and agreement for lengths of time in accordance with
Section 4.07.3.C. above.
(b) For all such plans that qualify for the five (5) year plan approval law (although
their approval will remain valid for five (5) years from their date of approval, even though their
performance agreement and bond may not be valid), the director of Planning may extend their
bond and agreement for lengths of time in accordance with Section 4.07.3.C. above.
4.07.4 Performance Bond Reductions.
A. Any form of guarantee may be partially released periodically (i.e., reduced) to an amount
not less than either ten percent (10%) of the project's highest bond value or not less than the
actual cost of completion, whichever is higher, plus permitted allowances in accordance with the
provisions of this section.
(1) All reduction requests shall be submitted in writing to the director of Planning. No
request shall be deemed officially received unless submitted in accordance with the following
requirements:
101
April 2000
(a) If an extension of the performance agreement is sought, every requirement for
an extension request must be met, including but not limited to, submission of written consent by
the surety to any such request;
(b) The request shall identify the project, performance agreement, bond, and
completion date and must specify the amount of reduction sought. It shall also contain a detailed
cost estimate, using the current County unit price list, of the remaining work and a projected
timetable for completion.
(c) A fee, covering any necessary inspection and administrative costs, shall be paid
in accordance with the fee schedule.
(2) Periodic partial bond reductions shall not occur before at least thirty percent (30%)
of the bonded improvements, including any cost adjustments necessary for pavement redesign in
accordance with Section 600.00 of the DCSM, if applicable, have been satisfactorily completed.
(3) The County shall not be required to execute more than three (3) reductions in any
twelve (12) month period, except as authorized by the director of Planning.
(4) No reduction shall be approved if the performance agreement is in default. However,
reduction requests may be considered concurrently with extension requests.
B. In such instances as the director of Planning deems appropriate, the developer shall
furnish a certificate of completion from a professional engineer or land surveyor, stating the work
described has been performed in strict conformity with either the approved final plans or as-built
plans submitted therewith, and that the work meets all applicable standards.
C. The director of Planning or the designee shall act upon any reduction request within thirty
(30) days of its official receipt. If the request is disapproved, the developer shall be notified in
writing of the specific reasons for disapproval. If no action is taken within the time specified, the
request shall be deemed approved and a partial release granted.
4.07.5 Performance Bond and Agreement Final Release Procedures.
A. All final performance bond release requests shall be authorized within thirty (30) days of
their official receipt, in writing, by the director of Planning, provided the following criteria have
been met:
(1) Acceptance of all public facilities by the state agency, local government department
or agency, or other public authority, which is responsible for maintaining or operating such
facility, and the completion and approval of any other bonded site-related improvements.
(2) Acceptance of as-built plans by the Department of Public Works.
(3) Payment by the developer of all required fees, proffers and contributions.
102
April 2000
B. If a final bond release is not authorized within the thirty (30) day period, the developer
may send an additional request, by certified mail, to the director of Planning. Within ten (10)
business days of the receipt of the request, the director of Planning shall either release the bond,
or notify the developer of the specific agency approval not received. If no action is taken, the
request shall be deemed approved and final release granted.
C. In the event any dedicated road cannot be taken into the state highway system for reasons
other than quality of construction, the developer may nevertheless seek release in accordance with
the provisions of this section, provided there is compliance with the requirements of Section
4.07.6 below.
D. In appropriate circumstances, the obligations of a performance agreement may be
suspended and the project's performance bond released, in accordance with the provisions of
Section 4.07.7 below.
4.07.6 Maintenance Bonds.
A. Whenever Prince William County has accepted the dedication of a road for public use and
such road, for reasons other than quality of construction, is not eligible for acceptance into the
state highway system, the developer may still (1) request release of the performance agreement
and bond, or (2) in the case of a successor developer, that successor developer may request to be
excused from entry into a substitute performance agreement and posting a construction
performance bond. In such instances, the developer shall post a maintenance and indemnifying
bond in lieu of the performance bond, provided that all other requirements for release are
otherwise met.
B. Such maintenance and indemnifying bonds shall meet the following requirements:
(1) The maintenance bond shall be in an amount approved by the director of Public
Works.
(2) It shall also be sufficient to indemnify Prince William County for:
(a) The expense of any maintenance of the streets, curb, gutter, appurtenant
drainage facilities, utilities, including correction of defects or damages and for the removal of
snow, water or debris, so as to keep such road reasonably open for public use, pending state
acceptance; and
(b) The expense of repairing or reconstructing such road to approved standards at
such time as the impediment to acceptance when first constructed is removed.
C. The maintenance bond shall be annually reviewed by the County for sufficiency of its
amount, status of roads, and the road maintenance being provided by the developer.
103
April 2000
4.07.7 Bond Deferral Option.
A. As noted at the outset, the obligation of the developer is to construct all public
improvements in a timely manner and obtain their acceptance by the appropriate public body after
construction. Similarly, it is the assumption and intention of Prince William County that the
scheme approved be realized within a reasonable period of time, inasmuch as over time the Board
of County Supervisors may amend ordinances and standards, and developments approved under
one ordinance may become outdated or substandard under later ordinances or regulations.
Nevertheless, the Board of County Supervisors is sensitive to the need for any option lying
between the extremes of:
(1) Requiring completion of all required improvements and their ongoing maintenance
under a maintenance bond until all standards for acceptance are met.
(2) Requiring, as a condition, the release of a performance bond and agreement that the
plat be vacated for those portions of the development in which improvements are not installed.
These provisions provide such an option. It is not an option intended to extend the
validity of approved plans without the initiation of construction.
B. The bond deferral option is available only upon written request by all owners of the
property affected, which must include the trustees on any deeds of trust and the beneficiaries for
whom they act.
C. Portions of the development which are constructed and occupied must be completed and
public improvements therein accepted by the appropriate public bodies. In appropriate
circumstances, partially occupied sections may be placed under security of a maintenance bond,
pending acceptance.
D. The owners of property for which the developer requests release of the performance
agreement and bond, under this section, shall execute an agreement, approved in form by the
director of Planning, which shall provide that:
(1) The owners agree not to convey or otherwise alienate the property, except in its
entirety, until such time as the bond deferral agreement has been discharged in accordance with its
terms.
(2) Breach of the agreement, or conveyance of any portion thereof, voluntary or
involuntary, shall be deemed an application by the owners, under Virginia Code sections
15.1-480, 481 and 482, for vacation of the plat pertaining thereto.
(3) No construction upon or improvement of the property may be made until the
developer has executed the standard performance agreement and tendered surety for performance
in the amount and form authorized under this policy.
(4) The validity period of such bond deferral agreement shall not exceed the validity
period of the final plans for the project in question.
104
April 2000
(5) Unless the developer has commenced construction, or entered into the customary
performance agreement, with performance bond required under this policy, under the approved
plat within the validity period of the bond deferral agreement, Prince William County may initiate
vacation of the plat under Virginia Code sections 15.1-480,481, and 482.
(6) The agreement shall be recorded among the land records, by the County, at the
developer's expense.
E. At the determination of the director of Planning, the developer shall execute a
maintenance bond, with approved surety, for public improvements partially or fully constructed
within the property, subject to an agreement under this section.
4.07.8 Default and Evaluation Procedures.
A. If the developer fails to complete the required site improvements in the period of time
specified in the agreement, or any approved extension, the developer is deemed in default.
B. The Office of Planning shall forward a report on the project to the Board of County
Supervisors, with the director of Planning's recommendation to formally declare the project to be
in default. Such recommendation shall also enumerate a recommended course of action in
response to default. Such recommendation may include the following, in any combination:
(1) That the county attorney be authorized to institute such actions as deemed
appropriate to enforce the provisions of this policy, the performance agreement and bond, and
applicable code provisions.
(2) That demand be made of the surety on the developer's bond for payment of the funds
secured thereby, for application to completion of the project, or for performance of its principal's
obligations.
(3) That the County contract for completion of the project.
(4) That all or any portion of the project be vacated.
(5) That any successor in interest to the defaulted developer be required to post an
adequate replacement performance agreement.
(6) That no additional building permits be issued for the project, subject to the bond,
until an adequate right of entry permit bond is posted with the County. Such a bond shall bind
and hold the applicant responsible for any and all damages to any public improvements already in
place, caused by work covered by the resulting right of entry permit and building permit. Such
bond shall be governed by the provisions of sections 4.07.2 and 4.07.5 of the procedures.
105
April 2000
C. The developer and surety will be mailed copies of the Office of Planning's report and
recommendation. They also will be advised of their opportunity to be heard on the matter at the
scheduled meeting of the Board of County Supervisors. Either the developer or the surety, or
both, may offer proposals for completion as alternatives to that of the recommendation of the
director of Planning. Any such proposal must be submitted in written form and signed by
someone with the appropriate authority to issue a binding proposal.
D. All defaulted projects shall be scheduled for completion in chronological order of their
declaration of default. Exceptions to a policy of first-in, first-out shall be made when the funds
associated with a bond or letter of credit are collected by Prince William County and cover the
cost to complete the bondable items, and the project is eligible for acceptance into the state
system. In such cases, the project shall be inserted into the existing project completion schedule
as the next project to be handled by Prince William County and/or its contractor.
4.07.9 Debarment of Surety.
A. Any person otherwise qualified in accordance with the requirements of this policy to act
as surety for any performance bond may nevertheless be disqualified from acting in such capacity
on any agreement to which the BOCS is a party, in accordance with the provisions of this section.
B. Whenever the director of Planning shall recommend to the Board that any person be
disqualified from acting as surety on any bond, the Board shall proceed as follows:
(1) Notice of such recommendation shall be served by certified mail on such person.
Such notice shall apprise such person of the grounds upon which such recommendation is made
and of the time and place the matter will be taken up by the Board of County Supervisors.
(2) Such person may appear and be heard on the matter.
(3) Following a hearing, the Board of County Supervisors may declare such person
ineligible from acting as surety satisfactory to the Board for such period of time not to exceed five
(5) years as it may specify, may defer its findings on such terms and conditions as it deems
appropriate, or may dismiss the recommendation of the director of Planning.
C. Any matter tending to establish that the surety will not perform in accordance with the
terms of the surety's contract commitment shall be grounds for disqualification. Specific reasons
for disqualification shall include but not be limited to:
(1) The surety commits an act of bankruptcy, reorganization, becomes insolvent,
bankrupt, makes an assignment for the benefit of creditors, consents to the appointment of a
trustee or receiver, or either a trustee or receiver is appointed for the surety or for a substantial
part of its property without its consent.
(2) The surety is presently in default of one or more bond contracts in which Prince
William County is obligated, or having breached a bond contract in the past, has failed to provide
reasonable assurances that it will discharge its obligations under the performance bond.
106
April 2000
(3) The surety is in default of one or more identical or substantially similar bond
agreements with any other political subdivision of the state.
(4) Any managing or policy-making officer of the surety, acting in the course of
employment or on behalf of the surety, is convicted under state or federal statues of
embezzlement, theft, forgery, bribery, falsification or destruction of records, fraud, or any offense
indicating a lack of business integrity or business honesty which substantially affects the surety's
responsibility/reliability as a surety for performance of duties on behalf of the owner to the
County.
(5) Any other cause the Board of County Supervisors determines to be so serious and
compelling as to affect responsibility as a surety, including debarment by another governmental
entity.
4.08 Land Development Permit Procedures for Final Site Development Plans.
Following the approval of final site development plans, permits must be obtained, and applicable
fees paid, prior to commencement of any land disturbance activities and/or construction of site
improvements.
4.08.1. General Requirements. Based upon the specifics of the project, the County requires
various land development permits, or a combination thereof, to be issued. They are:
A. Flood Hazard Use Permit (if applicable). This permit shall be obtained prior to any other
land development permits, and authorizes land disturbances in flood hazard areas.
B. A-1, Residential/Agricultural and Erosion Control Grading Permit. This permit will be
issued for instances where a site development permit is not required and the area of disturbance
exceeds five thousand (5,000) square feet (464.52 square meters), the maximum threshold for a
land disturbance permit. It shall cover the inspection of all items involved, including the
installation and maintenance of erosion and sediment control devices. All erosion control devices
must be inspected and approved by the Department of Public Works, prior to the initiation of any
land disturbing activity.
C. Site Preparation Permit: This permit shall cover the inspection of all construction items,
including erosion and sediment control devices, but excluding building and trades permits, which
are initiated in accordance with Section 4.04.10 above, prior to the posting of performance bonds
and agreements. The installation of the erosion and sediment control devices by the developer
shall be inspected and approved by the director of Public Works prior to the initiation of any other
land disturbing (construction) activities. This permit shall be replaced, at no cost to the
developer, when a performance bond and agreement has been posted by the developer.
107
April 2000
D. Site Development Permit. This permit shall cover the inspection of all land construction
items, including erosion and sediment control devices, but excluding building and trades permits.
The installation of the erosion and sediment control devices shall be inspected and approved by
the Department of Public Works, prior to the initiation of any other land disturbing activities.
This permit is valid as long as there is a valid performance agreement and bond posted in
accordance with Section 4.07 above.
E. Water and Sewer Installation Permit. This permit shall be obtained from the appropriate
utility for performance of inspections during installation of water and sewer facilities and
appurtenances, following the issuance of a site development permit or grading infrastructure
permit.
F. VDOT Land Use Permit. This permit shall be obtained from VDOT for both temporary
construction and permanent entrances prior to connecting to any highway in the state system.
G. Underground Utility Line Permit. This permit is obtained to allow the installation of all
underground conduits and their related facilities (gas, electric, cable television, telephone). Prior
to the issuance of this permit, the developer shall have obtained an approved set of construction
and/or early grading plans and a site development permit or a grading/grading infrastructure
permit. The underground utility line permit is valid for twelve (12) months. Extensions of the
validity period may be requested in writing to the Office of Planning.
H. Right of Entry Permit. This permit shall be obtained to allow construction on or passage
over County-owned property, including rights-of-way not in the state system and public
easements in which the County has an ownership interest. The applicant shall secure a permit
prior to commencement of construction. The director of Planning may require submission of such
engineering plans or profiles as deemed appropriate to allow proper review of the application.
The permit shall be issued only if the review indicates that the activity proposed is consistent with
the purposes for which the County holds the property and that there will be no adverse impact
upon the County's interest therein. Any activities permitted by the director of Planning, without
review and approval by the Board of County Supervisors, shall be temporary in nature and shall
not include permanent fixtures or improvements, with the exception of required and approved
improvements (e.g., driveways). Only those activities described in the permit are authorized.
I. Grading/Grading Infrastructure Permit. Once the initial review process has been
completed for nonresidential final site development plans, and the plans demonstrate substantial
compliance with development requirements, and no significant comments are outstanding, the
applicant may request a grading/grading infrastructure permit with the second submission of the
site development plan. Requests for grading/grading infrastructure permit shall be made in
writing to the director of Planning. The director of Planning or the designee shall, by letter,
authorize the submission of grading/grading infrastructure plans for signature approval before the
initiation of the grading/grading infrastructure permit issuance process.
(1) Once the plans are approved, a grading or grading infrastructure permit approval
letter will be prepared.
108
April 2000
(2) Upon approval of the grading/grading infrastructure permit, actual construction of
the development must be commenced and diligently pursued within a six (6) month period.
Failure to begin actual construction within this six (6) month period will void the permit. If within
this six (6) month period, the site development plan has not been approved, and the site
development permit issued, the grading/grading infrastructure permit will also be void. Upon the
voiding of such a permit, the developer shall commence the revegetation of the property in
accordance with the standards contained in Section 800.00 of the DCSM. Such revegetation shall
commence immediately upon notification by the Office of Planning of the voided grading/grading
infrastructure permit. The revegetation of the site shall be completed within thirty (30) days of
such notification, weather permitting. Failure to complete the revegetation within this time period
shall cause the director of Planning to use such escrow funds available to Prince William County
to complete such work. Actual construction is hereby defined to include the placing of
construction material in permanent position and fastened in a permanent manner.
J. Land Disturbance Permit. This permit shall be obtained to insure compliance with
Section 32-201.00 and 32-504.00 of the Zoning Ordinance and all other sections of the DCSM
when no other permits are required. It is required for any land disturbing activity exceeding two
thousand five hundred (2,500) square feet (232.26 square meters), but less than five thousand
(5,000) square feet (464.52 square meters). The applicant must submit a plan outlining proposed
disturbances and erosion and control practices.
(1) A house location survey, record plat, County topography map with a parcel overlay,
or a nonengineered outline of the lot, correctly drawn to scale, may be used as a basis for this
plan. The plan shall locate the disturbed area by offset distances to the property lines and shall
contain a signed statement, by the owner, that appropriate erosion devices will be provided.
K. Nonresidential Preconstruction Permit. Upon approval of a nonresidential
preconstruction plan, this permit shall be obtained prior to commencing any land disturbance
activities. The permit shall specify a validity period during which all grading and/or improvements
shown on the plan must be completed and the site must be stabilized. Failure to stabilize the site
may cause the director of Planning to use any escrow funds available to Prince William County to
complete such work.
4.09 Violation and Shutdown Notices and Procedures.
Construction activity on any site shall be conducted in strict accordance with the limits of clearing
and grading and shall be shown on plans approved by the director of Planning. Construction
activity shall also be conducted only on those items for which a permit has been obtained. Failure
to obtain required permits, or develop the site in accordance with approved plans, will necessitate
the County taking any and all necessary actions required to correct the situation.
109
April 2000
4.09.1 General Requirements. Such actions may include, but shall not be limited to the
following:
A. Posting of a stop work (construction) notice. Such notice shall be posted in a
conspicuous place on the site in violation by a representative of the agency responsible for the
inspection of the improvements being made, and also forwarded, by certified mail, to the
developer.
B. Issuing a written notice to the owner or responsible agent, from the agency responsible
for the inspection of the improvements, outlining the nature of the violation and requiring on-site
activity to cease and desist immediately. A copy of the notice shall be sent to all other agencies
responsible for inspections on that site.
(1) This notice will instruct all other agencies to revoke all permits which may have been
issued, cease making any further inspections on that site, and cease processing any plans for that
site, if the director of Public Works deems the violation to be of such a serious nature.
(2) If cooperation is not received from the owner or responsible agent and work is not
stopped immediately upon notice, a court injunction to stop work (construction) will be sought.
C. The director of Public Works may, if necessary or appropriate, seek criminal process
against any person who violates any provisions of the DCSM, and the issuance of a violation
notice and correction order shall not be deemed a precondition to the issuance of a warrant or
summons for such violation. In addition, the director of Public Works may seek immediate civil
relief, regardless of what other action has been or will be taken.
4.10 Priority Plan Processing.
4.10.1 Priority Site Development Plans. The processing of priority site development plans
shall be conducted in accordance with the time frames and requirements outlined in Section 4.04.4
above.
4.10.2 Priority Building Construction Plans. The processing of priority building construction
plans shall be conducted in the following manner:
A. Four (4) sets of construction plans, specifications, documents and trade permit
applications may be submitted to the Department of Public Works, Building Development
Division, simultaneously with the final site development plans. One additional set of construction
plans and specifications is required for any application involving food preparation and/or food
processing for foods intended for human consumption. Construction plans shall include all
architectural, structural, electrical, mechanical, plumbing, and gas drawings, as well as a site plan.
Upon receipt, they will be processed for review as follows:
(1) The application, plans and specifications will be transmitted to the appropriate county
and state agencies for review within two (2) days of their receipt.
110
April 2000
(2) Staff specified by the agencies shall respond with comments back to Public Works,
generally within twenty (20) business days.
(3) On the twenty-first (21st) day, or the next closest day convenient to the applicant, a
meeting shall be held with the applicant and those agencies requiring revisions to the plans in
order to reach a mutual understanding of code requirements.
(4) The architect or engineer shall submit revised plans back to the Department of Public
Works, Building Development Division. If the revised submission is not submitted within thirty
(30) days of the date of the meeting, the priority processing status is terminated and normal
processing will take effect. This period may be extended by the director of Public Works, upon
written request, if unusual circumstances warrant.
(5) If no further changes are required, plans will be approved as noted.
(6) Tenant layout plans will also be priority reviewed if received within six (6) months
after the review of the shell plan.
4.11 Expedited Plan Processing.
4.11.1 General Requirements. The processing of expedited site development plans shall be
conducted in accordance with the time frames and requirements outlined in Section 4.04.4 above,
Section 118.00 of the DCSM and the following:
A. All plans, including those prepared by designated plans examiners (certified in Prince
William County) will be submitted to quality control in the Planning Office.
B. Final plans prepared by a designated plans examiner (DPE) will automatically be
processed for expedited review.
C. During the first review of final plans, the comments generated and received in the
Department of Public Works will be reviewed and consolidated by a County designated plans
examiner.
D. DPE-prepared plans requiring a full review during second submission will automatically
lose their expedited review status and revert to a regular process plan.
E. The Planning Office will keep track of the number of plans submitted by DPEs that are
rejected by quality control or required more than one review prior to signature review. The
reason for quality control rejection will be indicated.
F. This information will be transmitted periodically to the Advisory Plans Examiner Board
for their information and use.
111
April 2000
4.12 As-built Plans.
As-built plans shall be required on all currently valid final site development plans. The acceptance
of as-built plans shall be a prerequisite to final construction acceptance, bond release, and the
issuance of a final certificate of use and occupancy. Copies of the as-built plans, prepared and
certified by a registered land surveyor or professional engineer, shall be submitted to the
Department of Public Works and the Service Authority at the time final inspections are
conducted. Final inspections will not be made unless the as-built plans are available.
4.12.1 General Requirements. The following information shall be included on the plans:
A. Horizontal locations of all sanitary sewers, storm sewers and waterlines, which include:
(1) Two (2) ties to all water valves or blow-offs. In cases where a group of valves may
be located at an intersection, two (2) ties may be provided to one (1) valve and the remaining
valves tied to each other;
(2) One (1) tie to all sanitary sewer manholes and storm sewer structure;
(3) Two (2) ties to all sanitary sewer cleanouts on laterals which are located within the
state road right-of-way, and the two (2) ties to the first clean out on a lateral connected to a main
within the state right-of-way.
(4) Location of all water meters, detector checks, fire-flow meters, fire hydrants, air
release valves, grease traps and any other water or sewer system appurtenances. The size of all
meters larger than three-fourths (3/4) inch (20 millimeters) is to be noted. All ties shall be affixed
to be easily located permanent objects (i.e., building corners).
B. Invert elevations on storm sewers and sanitary sewers.
C. Length, size, and type of material used for all storm sewer and storm water management
systems.
D. Top of structure elevations on all sanitary manholes and storm sewer structures.
E. As-built topography on storm water detention basins and verification of storage volumes.
F. Detailed as-built information for special design drainage and storm water management
structures.
G. Spot elevations showing inverts of improved channels and swales located in dedicated
drainage easements.
H. All dedicated easements. The cover sheet shall show the deed book and page number(s),
in which the water and sewer easements and/or subdivision plats are recorded.
I. A graphic scale.
112
April 2000
J. Any changes from the approved construction plans must be indicated by circling the
change in red.
K. A note certifying compliance of the site to approved plans and conformance of any
revisions to all applicable standards. The following certification shall be used:
This physical survey has been reviewed and, in my professional opinion, based upon my
knowledge, information, and belief, the design elements measured by the physical survey comply
with the approved plans. This review does not imply in any way that (i) inspections were made
during the construction, (ii) to the quality of the work, or (iii) to any element or structure not
visible or depicted on the physical survey.
4.12.2 Impervious Area Measure. In addition to the as-built, the professional engineer or land
surveyor shall provide the County with a measure of the impervious area of the site. This
information shall be shown on a standard form available from the Department of Public Works.
4.12.3 Compliance. The as-built plans and the impervious area information will be reviewed for
compliance with the requirements of this section during the final inspections. Any deficiencies
with the as-builts or the impervious area information must be corrected before final construction
acceptance is granted.
4.13 Appeal of Director of Planning's Decision.
All decisions by either the director of Planning or the director of Public Works are final. If the
director of Planning or the director of Public Works disapprove any plan submitted pursuant to all
processing requirements identified in this document or the DCSM, and the applicant of such plan
contends that such disapproval was not properly based on applicable state and local ordinances
and policies, he/she may appeal directly to the circuit court having jurisdiction over Prince William
County. Such appeal must be filed with the circuit court within sixty (60) days of the date of the
written disapproval by the director of Planning.
5.0 Certificate of Use and Occupancy
Certificates of use and occupancy shall be issued in accordance with Section 116 of the DCSM.
No occupancy permits shall be issued until all sidewalks and/or pedestrian systems, in the general
area of the units scheduled for occupancy, have been constructed, inspected, and approved. Upon
specific request, and due to weather or other conditions, this requirement may be modified by the
director of Public Works.

PDF Document reader online

This website is focused on providing document in readable format, online without need to install any type of software on your computer. If you are using thin client, or are not allowed to install document reader of particular type, this application may come in hand for you. Simply upload your document, and Docureader.top will transform it into readable format in a few seconds. Why choose Docureader.top?

  1. Unlimited sharing - you can upload document of any size. If we are able to convert it into readable format, you have it here - saved for later or immediate reading
  2. Cross-platform - no compromised when reading your document. We support most of modern browers without the need of installing any of external plugins. If your device can oper a browser - then you can read any document on it
  3. Simple uploading - no need to register. Just enter your email, title of document and select the file, we do the rest. Once the document is ready for you, you will receive automatic email from us.

Previous 10

Next 10