Techno-Economic Analysis of Solar photovoltaic power plant for PES Campus Shivamogga A case study
Department of EEE PESITM Shivamogga Page 1
CHAPTER 1
INTRODUCTION
The development of renewable energy sources (RES) is necessary for the
sustainable development of any country due to depleting fossil fuel level, climbing fossil
fuel prices across the world and more recently pressure for reduction emission level.
Among various renewable energy sources based technologies, the solar photovoltaic
technology (PV) for power generation is considered well-suited technology particularly
for distributed power generation. The large introduction of PV systems may replace or
postpone the extension of conventional central stations of electricity production and the
investment in grid reinforcement having a positive overall economic impact. The PV
system electric power is of particular value when it coincides with the peak demand, as
during the summer afternoon peak due to the use of air conditioning units. In addition to
this, solar photovoltaic (PV) systems can also increase the reliability of the system to
which they are connected, can also reduce transmission and distribution losses as they
generate the electricity close to the point where it is consumed.
PV systems are designed and sized to meet a given load requirement. PV
system sizing exercise involves the determination of the size and capacity of various
components, like PV panels, inverter, batteries, etc. PV system design also involves a
decision on which configuration is to be adopted to meet the load requirement. Once the
system configuration is decide then the size or capacity of the various components are
calculated. A low quality component (charge controller, for instance) may be cheaper
initially but probably will be less efficient and may not last longer. On the other hand, a
relatively expensive but higher quality component is more likely to perform better (saving
energy and thus cost) and may be able to recover its cost in the long run.
Most parts of India receive solar energy of 5 Kwh/m2 per day over 280 clear
days per annum. Even if 1% of this land is used to harness solar energy at an overall
efficiency of 10%, as much as 429 × 109 KWh/year of electricity can be generated. One
Techno-Economic Analysis of Solar photovoltaic power plant for PES Campus Shivamogga A case study
Department of EEE PESITM Shivamogga Page 2
of the states of India, Karnataka is rich in solar resources and solar energy will
complement the conventional sources of energy in a large way. The state of Karnataka is
blessed with about 240 to 300 sunny days with good solar radiation of 5.4 to 6.2
kWh/m
2
/day.
To harness the potential of solar resources in the state, Government of Karnataka
had issued a solar policy for the period 2014-2021 with the objective to achieve 3%
contribution from solar source out of total energy consumption. All solar power projects
(solar PV and solar thermal) established in the state of Karnataka shall be eligible for
benefits under the policy. The different projects applicable under this policy are
 Grid connect, utility scale projects
 Grid connect, roof top projects
 Off grid projects
In grid connect roof top project, all residential/institutional/commercial/government
building owners, industrial units are eligible to set up solar power plant within the
prescribed capacity limit.
The solar market for power generation is still relatively new and not completely
understood. There are a limited number of technology providers and access to technical
data is restricted. There is a need to analyze the energy impact of these systems before
large scale implementation of the technology.
In the ongoing work the potential and the cost-effectiveness of a solar photovoltaic
power plant for meeting the energy demand of PES campus, one of the educational
institution situated near Shivamogga (Karnataka) is to be analyzed. PES institute of
shivamogga comprises of seven blocks of buildings. Electricity is needed for lighting
gadgets, fan, air conditioners and to run various equipment and machineries.
The average energy demand of the institution is 4.79MW and it varied monthly.
These days getting a continuous and uninterrupted supply of energy has become the
largest problem for institution. The backup diesel generators have a very high operation
cost and are not a clean source of energy either. So there is great need for a sustainable
and clean source of energy. Solar energy is the largest available carbon-neutral renewable
energy source which can meet the energy demand of institution.

PDF Document reader online

This website is focused on providing document in readable format, online without need to install any type of software on your computer. If you are using thin client, or are not allowed to install document reader of particular type, this application may come in hand for you. Simply upload your document, and Docureader.top will transform it into readable format in a few seconds. Why choose Docureader.top?

  1. Unlimited sharing - you can upload document of any size. If we are able to convert it into readable format, you have it here - saved for later or immediate reading
  2. Cross-platform - no compromised when reading your document. We support most of modern browers without the need of installing any of external plugins. If your device can oper a browser - then you can read any document on it
  3. Simple uploading - no need to register. Just enter your email, title of document and select the file, we do the rest. Once the document is ready for you, you will receive automatic email from us.

Previous 10

Next 10